Item No. Date of Meeting 1947 Water Main Improvements Project Authorization (CIP #C801224) 8h_supp February 11, 2025 Requested Action Request Commission authorization for the Executive Director to: 1) transfer authorization and up to $3,200,000 of budget from the C801042 Landside Pavement Program to support additional pavement rehabilitation, and 2) take all steps necessary to complete the 1947 Water Main Improvements project located at Seattle-Tacoma International Airport. The amount requested for authorization is $12,200,000 for a total project authorization of $13,300,000. 2 Utility Master Plan Recommended Water System Utility Needs N Legend Capacity Condition Project Driven Vision 3 Project Purpose and Original Scope Purpose: Mitigate the risk of future critical failures of the existing 1947 water main, nearing the end of its service life. Original Scope of Work: • Rehabilitation of existing water main with Cured-In Place Pipe (CIPP) liner and surface restoration • Rehabilitation of S 182nd St entrance/exit roadways pavement (Landside Pavement Program C801042) CIPP Installation on Snoqualmie Pass 4 Project Development • During preliminary design project experienced significant cost increases due to water main operating pressure and construction requirements • Project scope changed to conventional pipe replacement since lower overall cost and longer service life • Included additional scope to address failing infrastructure at Bridge 2 and Terminal South Bus Stops 5 Project Location Main Terminal Landside Pavement, Bridge 2, and Terminal South Bus Stops Main Garage New water main 6 Project Budget and Schedule Original Budget: Current Budget: $2,263,000 $13,300,000 Preliminary Project Schedule: • Construction Start Q4 2025 • In-Use Date Q4 2026 Completed 30% Design Design-Bid-Build Project Delivery Cost increase due to: • Change to pipe replacement ($9.9M) • Bridge 2/South Bus Stops scope addition ($3.4M) Construction around 2026 FIFA World Cup moratorium dates 7 Cone of Certainty We are here 8 QUESTIONS? 9