COMMISSION AGENDA MEMORANDUM Item No. ACTION ITEM Date of Meeting DATE : February 4, 2025 TO: Stephen P. Metruck, Executive Director FROM: Keri Stephens, Director, AV Facilities & Capital Programs Eileen Francisco, Director, Aviation Project Management Group 8h February 11, 2025 SUBJECT: 1947 Water Main Improvements Project Authorization (CIP #C801224) Amount of this request: Total estimated project cost: $12,200,000 $13,300,000 ACTION REQUESTED Request Commission authorization for the Executive Director to (1) transfer authorization and up to $3,200,000 of budget from the C801042 Landside Pavement Program to support additional pavement rehabilitation, and (2) take all steps necessary to complete the 1947 Water Main Improvements project located at Seattle-Tacoma International Airport (SEA). The amount requested for authorization is $12,200,000 for a total project authorization of $13,300,000. EXECUTIVE SUMMARY The 1947 Watermain Improvement project's goal is to mitigate the risk of future critical failures of the existing 1947 water main. The Utility Master Plan (UMP) identified sections that are deficient or nearing the end of its serviceable lifespan that includes this section of the water main. The section of the water main has experienced multiple failures requiring emergency repairs, most recently in January 2021. The project will abandon the existing water main and replace it with a new water main in a new alignment. Additionally, the project is rehabilitating the pavement at the south terminal bus stops and S 182nd St entrance/exit roadways, and completing the structural rehabilitation, primarily the failed expansion joints, of Bridge 2 which is the exit ramp from Arrivals to the Northern Airport Expressway. JUSTIFICATION This project will support the Century Agenda goal to advance this region as a leading tourism destination and business gateway by meeting the region's air transportation needs through Template revised January 10, 2019. COMMISSION AGENDA - Action Item No. 8h Meeting Date: February 11, 2025 Page 2 of 5 improving vital facilities and infrastructure in a sustainable and cost-effective manner. The water main and bridge expansion joints have reached the end of their serviceable life and require replacement or rehabilitation. Diversity in Contracting The design of this project will utilize an existing Indefinite Delivery / Indefinite Quantity (IDIQ) Contract to provide design services. The contract has a 10% over-all Women Minority Owned Business Enterprise (WMBE) participation goal. As this project has federal funding, the project team will work with Diversity in Contracting department and the Washington State Department of Transportation (WSDOT) to establish additional Disadvantaged Business Enterprise (DBE) goals for the construction contract. DETAILS This section of the water main was constructed circa 1947 and provides domestic water to the Cooling Towers, Main Garage (including the North Toll Plaza), and Sound Transit light rail station at SEA. This section of water main also provides the required flow for fire suppression in the Delta and Alaska Airlines aircraft hangars. The project originally proposed to rehabilitate the existing water main by using a cured-in-place pipe (CIPP) liner within the host pipe. This approach was thought to be less costly than full replacement and would significantly extend the useful life of the water main. However, as the preliminary design effort progressed the costs for CIPP continued to increase and soon were at the level of full pipe replacement. Costs increased due to 1) the cost of a more specialized pipe liner due to the high operating pressure, and 2) the number and location of required access pits and associated traffic control and asbestos abatement. Port staff explored a full pipe replacement option and determined that this option represented a better overall investment for the Port. The project will replace the water main from south of the S 182nd St intersection with International Blvd along a new alignment ending north of the light rail pedestrian bridge. The entire length of watermain replaced will be approximately 2,400 linear feet. Additionally, improvements to Bridge 2 and the terminal South Bus Stops were included since those improvements are in the same work area. Scope of Work The water main rehabilitation scope is changed to conventional pipe replacement instead of cured-in-place-pipe (CIPP) and additional scope is added to the project: (1) Conventional Pipe Replacement will provide more reliable water main infrastructure at a lower cost with more manageable construction impacts than the original scope. (2) Bridge 2: Rehabilitate two expansion joints on Bridge 2 as well as complete minor structural and stormwater improvements addressing hazardous failed infrastructure. Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA - Action Item No. 8h Meeting Date: February 11, 2025 (3) Page 3 of 5 South Bus Stops: Replace the pavement and curb lines at the terminal south bus stops including the rental car busing operation, public transit, and airporters. This scope is identified for a future project but will have reduced construction impacts when combined with the 1947 Watermain project. The existing project will also deliver a portion of the Landside Pavement Program (C801042) since the pavement rehabilitation scope includes the S 182nd St entrance and exit roadways that are located above the water main. This work is supported by a PSRC Pavement Preservation grant funded by the Federal Highway Administration (FHWA) and administered by WSDOT. Schedule Activity Construction start In-use date 2025 Quarter 4 2026 Quarter 4 Cost Breakdown This Request Total Project Design Construction Total $1,200,000 $11,000,000 $12,200,000 $2,300,000 $11,000,000 $13,300,000 ALTERNATIVES AND IMPLICATIONS CONSIDERED Alternative 1 - Restore the existing water main pipe by CIPP lining only Cost Implications: $10,200,000 Pros: (1) Innovative repair method Cons: (1) (2) (3) (4) Major disruption to operations (lane closures, detours, roadway capacity reduction) Significant capital investment for shorter service life Requires more capital investment than initially budgeted Adjacent deficient infrastructure remains at Bridge 2 and at terminal South Bus Stops. This is not the recommended alternative. Alternative 2 - Replace the water main pipe only Cost Implications: $9,910,000 Pros: (1) (2) Lower capital investment for longer service life Manageable construction impacts Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA - Action Item No. 8h Meeting Date: February 11, 2025 Cons: (1) (2) (3) Page 4 of 5 $120,000 of project costs will need to be expensed due to the project scope change from CIPP to full replacement Requires more capital investment than initially budgeted Adjacent deficient infrastructure remains at Bridge 2 and at terminal South Bus Stops This is not the recommended alternative. Alternative 3 - Replace the water main pipe and rehabilitate Bridge 2 and the terminal South Bus Stops Cost Implications: $13,300,000 Pros: (1) (2) (3) Cons: (1) (2) Lower capital investment for longer service life (for water main portion) Manageable construction impacts Cost savings and reduced construction impacts from bundling adjacent improvements for deficient infrastructure at Bridge 2 and at terminal South Bus Stops $120,000 of project costs will need to be expensed due to the project scope change from CIPP to full replacement Requires more capital investment than initially budgeted This is the recommended alternative. FINANCIAL IMPLICATIONS Cost Estimate/Authorization Summary Capital Expense Total COST ESTIMATE Original estimate Previous changes - net Current change Revised estimate sub-total Budget transfer from C801042 (if approved) Revised estimate Total $2,263,000 $2,056,000 $8,861,000 $13,180,000 $3,200,000 $16,380,000 $0 $0 $120,000 $120,000 $0 $120,000 $2,263,000 $2,056,000 $8,981,000 $13,300,000 $3,200,000 $16,500,000 AUTHORIZATION Previous authorizations Current request for authorization Revised authorization sub-total Authorization transfer C801042 (if approved) Total authorizations, including this request Remaining amount to be authorized $1,100,000 $12,080,000 $13,180,000 $3,200,000 $16,380,000 $0 $0 $120,000 $120,000 $0 $120,000 $0 $1,100,000 $12,200,000 $13,300,000 $3,200,000 $16,500,000 $0 Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA - Action Item No. 8h Meeting Date: February 11, 2025 Page 5 of 5 Annual Budget Status and Source of Funds This project (C801224) was included in the 2025-2029 capital budget and plan of finance with a budget of $4,319,000. A budget of $8,861,000 was transferred from the Utility Master Plan Allowance (C801267) resulting in a zero net change to the Aviation capital budget. A budget transfer up to $3.2M will come from C801042 Landside Pavement Program. The funding sources will be the Airport Development Fund (ADF) and revenue bonds. Financial Analysis and Summary Project cost for analysis Business Unit (BU) Effect on business performance (NOI after depreciation) IRR/NPV (if relevant) CPE Impact $16,500,000 Multiple cost centers with airlines cost recovery at 51%. NOI after depreciation will increase due to inclusion of capital (and operating) costs in airline rate base. N/A $.03 in 2027 Future Revenues and Expenses (Total cost of ownership) The operations and maintenance costs are anticipated to be minimal. ADDITIONAL BACKGROUND The Utility Master Plan was completed at SEA and included four objectives: 1) investigate, analyze, assess the existing condition and capacity, 2) analyze future infrastructure needs to reliably meet demands of the Aviation capital program and proposed Sustainable Airport Master Plan projects, 3) recommend and prioritize projects for inclusion in the Aviation capital program, and 4) support SEA's sustainability goals with respect to water, energy, and emissions. The overall utility infrastructure needs were categorized as either condition/capacity, project driven, or vision. For the water utility system, that supports domestic water and fire suppression, four projects were identified for immediate implementation to address condition or capacity concerns. The 1947 Water Main Improvements project is one of those four projects. ATTACHMENT TO THIS REQUEST (1) Presentation slides PREVIOUS COMMISSION ACTIONS OR BRIEFINGS November 12, 2024 - The Commission authorized the Executive Director to take all steps necessary to complete the Landside Pavement Program project (C801042) for a total authorization of $9,320,000. September 13, 2022 - The Commission authorized the Executive Director to complete design of the 1947 Water Main Improvements project (C801224) for a total authorization of $1,100,000. Template revised June 27, 2019 (Diversity in Contracting).