North Employee Parking Lot Improvements
Construction Authorization
for Phase 3
8h_supp
Item No.
January 28, 2025Date of Meeting
Project Location
North Employee Parking Lot (NEPL)
• Parking for airport employees
• 4,122 parking stalls
• 11,000 average parking permits
2
24
th
Ave S
S 146
th
St
N
Project Purpose
Purpose:
Extend the life of the North Employee Parking Lot and improve customer
service and operational support.
Scope:
• Phase 1: Bus Shelter renovation and limited site features (Complete)
• Phase 2: Renewal of failing infrastructure (retaining wall, electrical feeders)
and way finding signage (Complete)
• Phase 3: Renewal of pavement and underlying failing infrastructure
(watermain, storm channel drains), and banner signage at shelters
• Evaluation of electric vehicle charging infrastructure expansion
3
Renewal of:
• Failing pavement
• Failing infrastructure (watermain,
storm channel drains)
• Banner signage at shelters
Project Scope (Phase 3)
4
Current Budget $19,320,000
• Phase 1 $2,422,000
• Phase 2 $8,878,000
• Phase 3 $8,020,000
Phase 3 Schedule Milestones:
• Construction Start: Q2 2025
• In-Use Date: Q3 2026
Work will occur during 2026 FIFA
World Cup (no passenger impacts)
Phases 1 and 2 are complete
Project Budget and Schedule (Phase 3)
5
Cost Certainty
6
NEPL Phase 3
Questions?
7