COMMISSION AGENDA – Action Item No. 8h Page 2 of 5
Meeting Date: January 28, 2025
Template revised June 27, 2019 (Diversity in Contracting).
To advance this region as a leading tourism destination and business gateway by
meeting the region’s air transportation needs by delivering vital facilities and
infrastructure in a sustainable and cost-effective manner.
To be the greenest and most energy-efficient port in North America by reducing air
pollutants and carbon emissions.
Diversity in Contracting
For Phase 1 the commitment for women and minority business enterprises (WMBE)
participation included both a design contract at seven percent, and a construction contract at
twenty-eight percent. For Phase 2 the commitment for WMBE participation included both a
design contract at ten percent, and a construction contract at twelve percent. For Phase 3 the
WMBE commitment for the design contract is ten percent. The project team is working with the
Diversity in Contracting Department to determine participation opportunities and will set an
appropriate aspirational goal for WMBE participation for the Phase 3 construction contract.
DETAILS
The NEPL provides 4,122 employee parking spaces for Airport tenants, service providers, and
airline employees. An average of 11,000 monthly parking permits have been issued for the use
of this facility. Airport Operations provides a 24/7 transit connection to the Main Terminal that
currently operates on a ten-minute headway. There are three Bus Shelter buildings in NEPL,
each approximately 2,000 square-feet in size, that provide a waiting area and restrooms in
support of the transit operations.
Scope of Work
The scope of work for this project is being delivered in three phases.
Phase 1 includes the minor remodel of all three bus shelters, the replacement of failed
electrical feeders, and other minor site improvements. This work is complete.
Phase 2 includes the replacement of a failing rockery retaining wall, the remaining electrical
feeders, and the parking lot wayfinding signage. This work is complete.
Phase 3 includes pavement rehabilitation and the replacement of failing infrastructure
(storm drainage channel drains and water main) and replacement of banner signage at the
three shelters.
Aviation is evaluating the expansion of electric vehicle charging infrastructure at NEPL. If the
expansion of EV charging infrastructure is pursued it will require additional budget and be
implemented as a fourth phase.
Schedule
Phase 3 Construction start 2025 Quarter 2
Phase 3 In-use date 2026 Quarter 3