Major Construction Unit Price Contract for
Dredging
Tin Nguyen – Director, Waterfront Project Management
Arthur Kim – Capital Project Manager, Waterfront Project Management
Item No.: 8d_Supp
Date of Meeting: January 28, 2025
Action Requested
Commission Authorization Request:
Request Commission authorization for the Executive Director to
advertise for bids and execute a major construction unit price
contract for future dredging projects for a total not-to-exceed
capacity of $12,000,000. No funding is associated with this
request.
2
Background
• Maintenance dredging is a vital part of the Port’s asset
management program. It ensures that deep draft vessels
calling at the Port can safely and without delays at the West
Waterway and the berths of T-18, T-30, T-46, and T-91.
• Unit price construction contracts allow for a more efficient and
consistent procurement of a contractor to perform similar
work at multiple terminals.
3
Contract Objectives
4
Target Substantial CompletionDredging Project
Q1 2026West Waterway High Spots
Q1 2026T-18 Maintenance Dredging
Q1 2027T-30 Maintenance Dredging
Q1 2027T-46 Maintenance Dredging
Q1 2027T-91 Maintenance Dredging
Each project will go through separate authorizations for design & construction.
Schedule
5
Action Requested
Commission Authorization Request:
Request Commission authorization for the Executive Director to
advertise for bids and execute a major construction unit price
contract for future dredging projects for a total not-to-exceed
capacity of $12,000,000. No funding is associated with this
request.
6