COMMISSION AGENDA – Action Item No. 8d Page 2 of 3
Meeting Date: January 28, 2025
Template revised June 27, 2019 (Diversity in Contracting).
Once the unit price contract is in place, executing a work authorization for each project should
take weeks and not months, making the Port more responsive to changing business needs.
Diversity in Contracting
The project team is working with the Diversity in Contracting Department to determine an
aspirational goal for WMBE participation on this construction contract.
DETAILS
Scope of Work
Utilizing the Major Construction Unit Price Contract will allow for the early procurement of a
contractor and enables construction to begin as early as Q4 of 2025. The following maintenance
dredging projects are planned for the coming years. Each project will go through separate
authorizations for design and construction.
(1) The West Waterway High Spots Dredging to begin construction in Q4 of 2025 and target
completion in Q1 of 2026.
(2) The T-18 Maintenance Dredging Project to begin construction in Q4 of 2025 and target
completion in Q1 of 2026.
(3) The T-30 Maintenance Dredging Project to begin construction in Q4 of 2025 and target
completion in Q1 of 2027.
(4) The T-46 Maintenance Dredging Project to begin construction in Q4 of 2026 and target
completion in Q1 of 2027.
(5) The T-91 Maintenance Dredging Project to begin in construction of Q4 of 2027 and
target completion in Q1 of 2028.
Schedule
Activity
Commission authorization 2025 Quarter 1
Advertise 2025 Quarter 1
Execute Contract 2025 Quarter 3
Construction starts 2025 Quarter 4
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 – Do nothing.
Cost Implications: Expense funds will still be used in future years as separate projects.
Pros:
(1) Retain Port resources for other priority projects and financial initiatives.
(2) Defer temporary construction impacts at the Terminals.