Original Budget: $7,600,000
Current Budget: $7,000,000
Completed 30% Design
Project primarily funded by
Customer Facility Charge revenues
Preliminary Project Schedule:
• Design Start Q3 2024
• Construction Start Q2 2025
• In-Use Date Q1 2026
Design-Bid-Build Project Delivery
Project Budget and Schedule