This report is a matter of public record, and its distribution is not limited. Additionally, in accordance with
the Americans with Disabilities Act, this document is available in alternative formats on our website.
INTERNAL AUDIT REPORT
Operational Audit Capital
Terminal 117 Sites 2325 Restoration Project Closeout
January 2020 August 2024
Issue Date: November 12, 2024
Report No. 2024-18
Terminal 117 Sites 2325 Restoration Project Closeout
2
TABLE OF CONTENTS
Executive Summary ................................................................................................................................................. 3
Background ............................................................................................................................................................. 4
Audit Scope and Methodology ............................................................................................................................... 5
Appendix A: Risk Ratings ......................................................................................................................................... 6
Terminal 117 Sites 2325 Restoration Project Closeout
3
Executive Summary
Internal Audit (IA) completed an audit of the Terminal 117 Sites 23 25 Restoration Project Closeout
(Project) for the period January 2020 through August 2024. The audit was performed to provide an
independent assessment of performance, with the purpose of determining how goals and objectives
were achieved and to determine if there were opportunities for improvement in future projects.
This Project was executed as a Heavy Civil General Contractor/Construction Manager (GC/CM) delivery
method. The Port of Seattle (Port) entered into an Agreement with Scarsella Brothers Inc. with a
Maximum Allowable Construction Cost (MACC) contract in the amount of $14.2 million. Upon completion
of the Project, the Port performed a final cost reconciliation and resolved open change orders resulting
in the final contract being reduced to $13.6 million. We noted the Port’s Construction Management
Department’s Standard Operating Procedures (SOPs) are thorough and address the highest risks
usually seen in the closeout phase of construction projects.
We found that the Port’s process during the closeout of this Project was effective and met
industry standards. We do not have any reportable issues.
Glenn Fernandes, CPA
Director, Internal Audit
Responsible Management Team
Karen Goon, Deputy Executive Director
Sofia Mayo, Acting Director of Central Procurement Office
Brian Sweet, Director of Engineering Construction Management
Janice Zahn, Chief Engineer
Terminal 117 Sites 2325 Restoration Project Closeout
4
Background
Between 1937 and 1993, the Duwamish Manufacturing Company and Malarkey Asphalt Company used
the site for asphalt shingle manufacturing which left the site with contaminated soil and sediments. The
Port acquired the land in 1999, which was designated as an Early Action Area (EAA), as part of the
Lower Duwamish Waterway Superfund site by the U.S. Environmental Protection Agency (EPA). The
Port and the City of Seattle worked together to conduct multiple large-scale cleanups with EPA oversight.
The large-scale cleanups were done in two phases. The first phase was for the uplands and sediments
cleanup, which included the removal of pavement, derelict structures, and about 60,000 tons of soil and
sediment. Following that, another round of cleanup was done for streets and stormwater. This work
included storm drainage pipes under the streets, sidewalks, environmentally friendly landscaping,
installation of art, signage, and rain gardens which will improve the stormwater quality. These two
phases were completed in 2015 and 2016, respectively.
Beginning in 2020, the Port broke ground on the Duwamish River People’s Park, with the purpose of
restoring 14 acres of habitat and shoreline access on the west bank of the Lower Duwamish Waterway
in South Park, Seattle. This Project contributes to salmon recovery in the region, which can also support
the endangered Southern Resident Orca population. This area along the river is also used by tribal
fishers to harvest chinook, coho, pink, chum, and steelhead salmon as they practice their Treaty Fishing
Rights during salmon migration season.
This Project was unique in that it established the Port’s first “habitat credit bank”, which enabled third
parties to invest in habitat projects, as mitigation credits to comply with the Clean Water Act and the
Endangered Species Act. Any revenue generated by the Port will help fund additional habitat restoration
projects in the Green-Duwamish Watershed and Elliott Bay. In addition, the site serves as a learning lab
for environmentalists seeking skills training and hands-on experience with careers in habitat restoration
and marine wildlife conservation.
Some of the park’s features include:
Pathway and bridge to 275-foot-long pier
Gathering area, seating, and entrance to shoreline pathways and viewpoints
Public art and interpretive features
Interpretive trail to half acre restored marsh and riparian area
Marsh platform and steppingstone pathway
Hand-carried boat launch
Five and a half acres of restored marsh and native riparian shoreline
Seven hundred and fifty feet of lighted pathway to viewpoints and interpretive information
Access stairway to 35-foot-high waterway and habitat viewing platform
The Port contracted with Scarsella Brothers Inc. as the GC/CM of the project in August of 2020. The
original contract amount was $14.2 million. The final contract amount was $13.6 million, including the
executed change orders and the closing of open change order trends.
Source: Duwamish River People's Park | Port of Seattle (portseattle.org)
Terminal 117 Sites 2325 Restoration Project Closeout
5
Audit Scope and Methodology
We conducted the engagement in accordance with Generally Accepted Government Auditing Standards
and the International Standards for the Professional Practice of Internal Auditing. These standards
require us to plan and execute the engagement to obtain sufficient, appropriate evidence to support our
findings and conclusions based on the engagement objectives. We believe the evidence obtained
provides a reasonable basis for our findings and conclusions.
The period audited was January 2020 through August 2024 and included the following procedures:
Process Review
Obtained and reviewed the audit report written by Branch, Richards & Co., P.S.
Obtained an understanding of the closeout process through interviews with the Construction
Management team
Reviewed closeout process Standard Operating Procedures
Verified that the Port performed a cost reconciliation
Reviewed and compared the GC/CM job cost ledger with the final pay application
Reviewed self-performed work items for risks associated with lump sum self-performed work
Reviewed Water Treatment bid calculation details
Terminal 117 Sites 2325 Restoration Project Closeout
6
Appendix A: Risk Ratings
Observations identified during the audit are assigned a risk rating, as outlined in the table below. Only
one of the criteria needs to be met for an observation to be rated High, Medium, or Low. Low rated
observations will be evaluated and may or may not be reflected in the final report.
Rating
Financial/
Operational
Impact
Internal
Controls
Compliance Public
Commission/
Management
High Significant
Missing or
partial
controls
Non-compliance
with Laws, Port
Policies,
Contracts
High probability
for external audit
issues and / or
negative public
perception
Requires
immediate
attention
Medium Moderate
Partial
controls
Not
functioning
effectively
Partial
compliance with
Laws, Port
Policies
Contracts
Moderate
probability for
external audit
issues and / or
negative public
perception
Requires
attention
Low Minimal
Functioning
as intended
but could be
enhanced
Mostly complies
with Laws, Port
Policies,
Contracts
Low probability
for external audit
issues and/or
negative public
perception
Does not
require
immediate
attention