
Port of Seattle – Construction Audit Services Annual 2024 Satus Report
Report Date: December 5, 2024
R. L. Townsend & Associates, LLC
Concourse C-1 Building Expansion
Project Status:
Audit Activities:
• Pre-Construction
o All EC/CM, MC/CM and EW/CM pre-construction billings to date (Pay Apps 1-36) were
reviewed in accordance with the contract. Supporting documentation was reviewed for all pay
applications.
o The pre-construction items were resolved via discussions with the Port of Seattle. A formal
Exhibit of allowed personnel is still pending. This is the last item needed to close out pre-
construction.
• Construction
o All EC/CM, MC/CM and EW/CM billings to date (Pay Apps 1-23) were reviewed in accordance
with the contract. Supporting documentation was reviewed for all pay applications.
o Bluebeam Studio is used to review construction payment applications. All initial comments are
placed within Bluebeam Studio. All responses to audit questions/comments are provided via
email.
o Notable items within the pay app reviews included the following:
▪ VECA: VECA has been billing overscale rates that were not previously approved by POS.
POS confirmed the overscale base rates would be paid if VECA could justify the overscale
rates via certified payroll. The audit team is going through the process of verifying the
overscale rates.
▪ VECA: Audit team identified items shipped to personal residential addresses and other
non-project specific locations. These items have been removed from the pay application.
▪ VECA: Audit team identified items that were shipped to VECA’s home office that were
not project related and were not accepted by the POS Project Team. These items have
been removed from the pay application. We have asked POS for specific approved
shipping locations for materials. Any materials not shipped to these locations will be
questioned on future pay applications.
▪ VECA: An audit is currently being conducted by the Port to confirm materials shipped to
general warehouses (owned by subcontractors) are designated for the project.
▪ Apollo: Audit team has identified labor rates billed which either were declined by POS or
not approved. We are awaiting credit adjustments for these items.
GC/CM
EC/CM Subcontractor
Phase
Pre-construction Construction Pre-construction Construction Pre-construction Construction
Contract Signature 9/30/2021 8/16/2022 8/12/2022 8/12/2022 1/9/2023 1/6/2023
Original Contract Value
$ 194,000 $ 150,694 $ 194,000 $ 113,445 $ 246,486 $ 5,239,538
$ 277,000 $ 55,476,711 $ 80,037 $ 38,737,042 $ 106,250 $ 4,812,600
$ 471,000 $ 55,627,405 $ 274,037 $ 38,850,487 $ 352,736 $ 10,052,138
Billed as of September 2023
$ 470,969 $ 274,037 $ 350,050
Billed as of September 2024
$ 8,126,096 $ 2,961,532 $ 2,286,175
VECA Electric & Technologies, LLC
Apollo Mechanical Contractors
Project: Phase C-1 Building Expansion