
TSE Phase 2 Bollards and ADA Ramps Project
Executive Summary
Internal Audit (IA) completed an audit of the TSE Phase 2 Bollards and ADA Ramps Project (Project)
for the period February 2022 through July 2024. The audit was performed to provide a systematic and
independent examination of the quality of the Port of Seattle’s (Port) monitoring of the Project, to
determine if best practices were being followed, to verify compliance with contractual requirements, and
to identify potential risks that may affect the Project’s schedule and budget.
The Port utilized a Design-Build with a lump sum delivery method, plus certain scope of work line items
that were reimbursed on a cost of work basis. The intent of the project was to create accessibility and
safety enhancements to the Main Terminal Arrivals and Departures curbsides, and in the main garage
at the pedestrian sky bridge entrances and Courtesy Vehicle Plaza.
The original contract agreement between Hoffman and the Port was approximately $13.8 million. During
the Project, there have been approximately $101K in change orders and an additional 80 days added
to the schedule, primarily because of unknown varying site conditions identified during the project.
Additionally, there is currently approximately $111K in Open Trends and an additional 50 days that may
be added to the schedule because of discretionary, Port requested changes, that occurred after the
Project began. The total projected cost is anticipated to be approximately $14 million.
Although the Project encountered multiple difficulties, primarily because of the lack of adequate
management between Hoffman and the subcontractors, we did note that the Port’s Project team was
diligent in monitoring these issues and held the Contractor accountable to complete the Project as
required in the Agreement.
In general, Port management followed policies and Standard Operating Procedures (SOP). However,
we identified opportunities where internal controls could be enhanced or developed. These opportunities
are listed below and discussed in more detail beginning on page six of this report.
1. (Medium) The failure to verify all required insurance coverages before project commencement risked
non-compliance with contractual terms, potentially leading to disputes, delays, or increased costs.
2. (Low) The Port started joint sealant work without creating a change order, risking project budget
integrity and potentially violating contractual obligations.
Glenn Fernandes, CPA
Director, Internal Audit
Responsible Management Team
Sofia Mayo, Assistant Director of Central Procurement Office
Karen Goon, Deputy Executive Director
Janice Zahn, Chief Engineer
Brian Sweet, Director of Engineering – Construction Management