Parking Garage Elevator Modernization Project
Schedule of Observations and Recommendations
Removal of important material specifications during the bidding phase resulted in post award
change orders that are expected to increase the cost of the contract by $3.5 million and as a
result, the Port will incur additional soft costs of $284,856.
During the procurement and bidding phase, the Port issued five addenda. We noted that in Addendum
5, a Port employee erroneously crossed out expected material and pattern specifications in the elevator
car finishes, without Port oversight catching the error, prior to the Addendum’s release (See Appendix
B). During construction, the contractor identified this error which resulted in five change orders that will
potentially cost the Port $3.5 million and add an additional 166 days to the project’s schedule. The Port
has estimated that its daily soft costs to oversee the Project are $1,716. This will result in an additional
$284,856 in soft costs that the Port will incur. Finally, an error in artwork (photographs) resulted in
additional glass and lighting, which led to an avoidable cost of $191,500.
CPO Procedure Section 2_Pre Award_2_5_ Advertisement Period mandates notification to the
Construction Manager (CM), Project Manager (PM), and Resident Engineer (RE) for all addenda, but
lacks a requirement for their sign-off. Moreover, although the procedure mandates a peer review before
posting, it does not specify the responsible party or their qualifications, and it does not mandate
documentation and retention of peer review evidence. Furthermore, there was a notable absence of
explicit mention of a final review, or approval step before publication. We were unable to obtain evidence
of a peer review, or final approval, of Addendum 5 because of personnel turnover and the lack of
documentation.
We also noted an additional concern during our review of change orders:
• A Port estimate was not performed for Change Order #1 which was approved on a Not-to-Exceed
(NTE) amount of $74,000. Port Standard Operating Procedures (SOPs) require an estimate for any
changes greater than $50,000.
Recommendations
1.1 Revise the CPO procedure to specify required approvers prior to issuing addenda and maintain
sufficient documentation.
1.2 Port estimates should be performed in accordance with SOPs.
Management Response
1.1 CPO agrees with the recommendation and will revise the CPO procedure to specify required
approvers prior to issuing addenda and maintain sufficient documentation.
1.2 Engineering Construction Management (CM) acknowledges the required estimate was missing from
the Not-To-Exceed Change Order (CO) 01 documentation. Per Standard Operating Procedures, CO 01
requires a reconciling change order to execute the final amount for the change. This provides an
opportunity for the project team to include an independent estimate in the reconciling change order.
Targeted training will also be done with the CM Resident Engineers and CPO Contract Administrators
on this topic during our Bi-Monthly training session.