Fishermen’s Terminal ADA Compliance Phase 2:
Additional Funding and Construction
Authorization Request
Item No.: 8g_Supp
Date: April 16, 2024
Commission Meeting | April 16, 2024
Jennifer Maietta Director, Real Estate Asset Management
Julie Yun Waterfront Capital Project Manager
Action Requested
Request Commission Authorization from the Executive Director to:
Request Commission authorization for the Executive Director to 1.
Approve additional funding, and 2. Advertise and execute a major public
works construction contract for the completion of the U00721
Fishermen’s Terminal ADA Compliance Phase 2 Project (CIP# C801198).
This request is in the amount of $1,100,000 for a total estimated project
cost of $2,890,000.
2
Project Background
Litigation Settlement Agreement (10/5/2020):
Port committed to address alleged Americans with Disabilities Act (ADA) code violations
within the Fishermen’s Terminal parking areas by 10/5/2022.
Phase 1 FT ADA Compliance (C801198/U00658)
Construction completed by Port Construction Services (PCS): 1/8/2023
Third-party post-construction survey reported remaining areas out of compliance with
2010 ADA design standards (e.g., ramps were too short and steep).
Phase 2 FT ADA Compliance (C801198/U00721):
Scope: Correct ramps, sidewalks and parking areas that are out of compliance
(demolition, regrading, paving/pavement overlay, pavement marking, landscaping)
Construction will be performed by an external general contractor procured via major
public works construction contract.
3
Risk Mitigation
Construction resource will be procured via Major Public Works
Construction contract to establish contractual accountability
and not-to-exceed cost limit for full delivery of design.
Engagement of the new Port Facilities Access Program
Manager specializing in ADA requirements for review and
guidance through duration of project.
4
Tenant Impact Mitigation
Tenant impact will be minimized through the following
coordination:
External relations outreach and coordination.
Additional tenant-specific communication by on-site Real Estate and
Maritime Operations staff.
Construction contract terms to include access and phasing
accommodation
Timing of work to commence October 2024 after busy season.
Internal coordination to limit conflict with other projects occurring at
Fishermen’s Terminal.
5
Funding Request
Additional Funding Request: $1,100,000
Justification:
1. Tenant Impact: Minimize tenant impact through construction phasing and
outreach.
2. Compliance: Phase 1 original construction did not meet ADA compliance
requirements per project design. Phase 2 re-work will be required to meet full ADA
compliance via external construction contract.
3. Litigation: The conditions of the Litigation Settlement Agreement have not been
met, as Phase 1 construction did not meet ADA compliance requirements per
project design.
4. Funding: Current project funding has been exhausted as of Phase 1 original project
completion. Additional funding required to proceed with Phase 2 re-work scope.
6
Timeline
7
Milestone Date
Commission Additional Funding and Construction Authorization Apr 2024
Advertisement Jun 2024
Phase 2 Construction start Oct 2024
Phase 2 Substantial Completion Dec 2024
Questions