
COMMISSION AGENDA – Action Item No. 8g Page 2 of 6
Meeting Date: April 16, 2024
Template revised June 27, 2019 (Diversity in Contracting).
JUSTIFICATION
This project is driven by the litigation settlement agreement that commits the Port of Seattle to
deliver improvements at Fishermen’s Terminal to comply with 2010 ADA design standards. Port
Construction Services (PCS) executed construction of these improvements in the original Phase
1 FT ADA Compliance project in 2023. To demonstrate ADA compliance of the Phase 1 work, a
post-construction survey was performed by University of Washington ADII. This survey showed
the cross slopes and running slopes for some ramps, sidewalks, and parking areas to be out of
compliance with the 2010 ADA design standards. Phase 2 of the FT ADA Compliance project will
address the re-work of these areas that remain out of compliance from the original (Phase 1)
project scope.
Forward progress with Phase 2 re-work is currently paused until additional funds are available
and construction authorization is approved. Reason(s) for this request are as follows:
1. Tenant Impact: Minimize tenant impact through outreach and construction phasing.
2. Funding: Construction and post-construction survey of Phase 1 was completed in 2023.
As such, current funding authorization for the original project scope has been exhausted.
3. Compliance: Phase 1 construction performed by Port Construction Services did not meet
full ADA compliance requirements per the project design. Phase 2 re-work will be
required to meet full ADA compliance.
4. Litigation: The conditions of the Litigation Settlement Agreement have not been met, as
Phase 1 construction did not meet full ADA compliance per project design.
To mitigate risk and ensure successful Phase 2 execution, the project team will incorporate
changes to the original Phase 1 construction as follows:
1. Cost Controls: The construction resource will be procured via Major Public Works
Construction contract, thereby establishing contractual accountability and cost control
mitigation against potential re-work needs.
2. ADA Assistance: Engagement of the new Port Facilities Access Program Manager for
review and guidance through the duration of the project.
3. Tenant Impact Mitigation:
a. External relations outreach and coordination.
b. Additional tenant-specific communication by on-site Real Estate and Maritime
Operations staff.
c. Construction contract terms to include access and phasing accommodation.
d. Timing of work to commence October 2024 after busy season.
e. Internal coordination to limit conflict with other projects occurring at Fishermen’s
Terminal.