Airport Terminal Solid Waste Project
Commission Meeting
April 16, 2024
Item No. 8d_supp
Meeting Date: April 16, 2024
Central Terminal North Building
2
• Request addresses tenant view
conflicts at the Central
Terminal Wall.
• Scope includes lowering the
North building by over 7 feet
and the addition of a Green
Roof.
3
• Added sense of nature to
hardscape
• Reduced solar gain at Window
Wall
• Secondary stormwater benefits
Advantages of Green Roofs in this Application
Green Roof Installed at the Port-owned
World Trade Cetner on Alaskan Way
Project Cost and Schedule
4
Cost Breakdown
This Request
Total Project
Total
$4,500,000
$19,180,000
Schedule
Construction Re-Start: Q4 2024
Project in Use: Q2 2025
We are here
Action Requested
(1) Increase the project scope and associated budget for the Terminal
Solid Waste project in the amount of $4,500,000.
(2) Advertise, bid, and execute a major works construction contract,
execute related project change orders, amendments, work
authorizations, purchases, contracts, and take other actions
necessary to support and deliver the Airport Terminal Solid Waste
Project.
(3) Use Port crews for construction support.
Total project authorization of $19,180,000.
5