Justification
ï‚§ Project is currently within authorized budget, but is trending to
exceed authorized contingencies and require additional funds
to reach substantial completion due to:
– Varying site conditions associated with underground utility work.
– Resolution of the large quantity of Change Orders (CO) to address
numerous design discrepancies, resequencing of critical
construction work, and discretionary changes.
3