Terminal 5 Southeast Habitat Restoration:
Design Authorization and Preconstruction
Services Request
(CIP# C801246)
Item No.: 8k_Supp
Date: December 10, 2024
Julie Yun – Capital Project Manager, Waterfront Project Management
Jon Sloan – Senior Manager, Environmental Planning, Permitting, & Compliance
Agenda
Commission Request
Project Background
Project Scope
Timeline
2
Action Requested
Commission Authorization Request:
Request Commission authorization for the Executive Director to approve
design authorization to (1) complete design and permitting, and (2)
Award and Execute a Pre-construction Services Contract via Heavy-Civil
General Contractor/Construction Manager (GC/CM) delivery method. The
total request for this action is in the amount of $1,500,000 (total
authorization $1,715,000).
3
Project Objectives
4
Stabilize eroding shoreline using sustainable
alternative stabilization techniques.
Remove structurally compromised and
condemned T5SE building (Mission to
Seafarers building).
Optimize use of underutilized real estate
with no revenue-generating opportunity.
Protect against possible exposure to
contaminated soils and impact to utilities.
Generate Natural Resource Damages (NRD)
and/or Endangered Species Act credits.
5
Current/Future State of Project
FUTURE
CURRENT
Project Schedule
6
Anticipated DateItem
Q4 2024Commission Design Authorization
Q1 2025Heavy Civil GC/CM Procurement start
Q3 2025Preconstruction Services Contract Execution
Q4 2026Design & Permitting Complete**
Q4 2026Commission Construction Authorization
Q1 2027Construction Start
Q4 2027Substantial Completion
**Pending Trustee design review and permitting schedule.
Questions?
7