Template revised January 10, 2019.
COMMISSION
AGENDA MEMORANDUM
Item No.
8j
ACTION ITEM
Date of Meeting
December 10, 2024
DATE : November 1, 2024
TO: Stephen P. Metruck, Executive Director
FROM: Sarah Cox, Director Aviation Environment and Sustainability
John Evered, Senior Manager, Aviation Environment and Sustainability
SUBJECT: Authorization of Interlocal Agreement V, Des Moines Creek Basin Plan
Amount of this request:
$0
Total project cost:
$89,304 per year
ACTION REQUESTED
Request Commission authorization for the Executive Director to execute Interlocal Agreement
(ILA) number V with the Cities of Des Moines and SeaTac for continuation of the Des Moines
Creek Basin Plan for a period of 20 years with a financial contribution of $89,304 per year.
EXECUTIVE SUMMARY
The Port, the Cities of Des Moines and SeaTac, and previously King County and the Washington
State Department of Transportation have participated in four prior Interlocal Agreements to
design and permit projects to address drainage, flooding erosion, fish habitat and water quality
issues in Des Moines Creek from a regional, basin-wide approach. During the 4th ILA (executed
April 2004) the Basin Committee completed construction of a Regional Detention Facility (RDF),
High Flow Bypass Pipeline, Habitat Enhancement Basin Plan Restoration Projects, replacement of
a Culvert on Marine View Drive to improve fish passage, and a low flow augmentation project to
provide adequate flow in Des Moines Creek during low flow periods. This ILA also identified
respective jurisdiction operations and maintenance and funding contributions.
The 5th ILA will provide the means to continue to fund Basin restoration activities such as ongoing
operation and maintenance (O&M), replacement and improvement of existing projects including
adaptive management activities, ongoing monitoring of existing projects for permit compliance
and effectiveness, invasive vegetation monitoring and control, education and outreach and a
needs assessment to further address surface water and fish habitat issues within the basin.
JUSTIFICATION
The Basin Plan supports the operation of Seattle Tacoma International Airport and follows the
environmental priorities of the Aviation Environment and Sustainability Program. Completed
COMMISSION AGENDA Action Item No. 8j Page 2 of 5
December 10, 2024
Template revised June 27, 2019 (Diversity in Contracting).
projects will continue to stabilize the flow regime and reduce erosion in Des Moines Creek from
the airport property and surrounding jurisdictions to the Puget Sound. The regional detention
facility mitigates high flows, and routes base flow away from Des Moines Creek subsequently
lowering in stream erosion. As a result of the Des Moines Creek Basin Detention Standard, the
surface area needed to mitigate new development within the basin is approximately 40% to 60%
less than usually required. Several habitat improvements will continue to be monitored, such as
the placement of large wood and rock in Des Moines Creek that increased channel and habitat
complexity, reduced erosion, and reconnected floodplain-wetland habitats.
The new ILA will also continue to allow for collaboration to solve cross jurisdictional problems
with the other parties, and due to the annual contributions from the Cities of Des Moines and
SeaTac, O&M and replacement costs for facilities on Port property will be lower.
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 Do not approve the 5
th
ILA and terminate participation in the Des Moines Creek
Basin Committee.
Cost Implications:
Pros:
(1) No annual requirement for annual contributions.
Cons:
(1) This option would negatively impact local community partnering and increase the Port’s
and other participants costs of individual efforts to protect Des Moines Creek.
(2) This would remove the Port from regional efforts to develop solutions to environmental
issues facing local jurisdictions. The Port would not receive contributions from other
committee members and would have to perform O&M and replacement and
improvement projects on its own.
This is not the recommended alternative.
Alternative 2Approve the 5
th
ILA and continue participation on the Basin Committee
Cost Implications:
Pros:
(1) This option would allow for continued participation in a cooperative effort to mitigate
cross jurisdictional problems.
(2) This is the most cost-effective option to perform required O&M and replacement and
improvement tasks due to contribution from other local jurisdictions.
(3) The flood control and detention facilities governed by the ILA are critical to SEA
stormwater management in addition to the Des Moines Creek basin. The facilities
COMMISSION AGENDA Action Item No. 8j Page 3 of 5
December 10, 2024
Template revised June 27, 2019 (Diversity in Contracting).
mitigate high flows and route water to Ponds for detention. This ensures that the
facilities are maintained and continue to meet basin plan condition requirements.
Cons:
(1) Required annual contribution.
This is the recommended alternative.
FINANCIAL IMPLICATIONS
Annual Port contributions are calculated based on percent impervious surfaces with the basin;
37.21% by the Port, 46.14% by the City of SeaTac and 16.65% by the city of Des Moines. The
calculation used impervious surface data from a 2017 analysis and excludes approximately 249
acres of STIA’s Industrial Wastewater System that drains directly to the Puget Sound. Annual Port
O&M Fund and Replacement and Improvement Fund contributions will be $22,236 and $66,978
respectively, for a total of $89,304 per year.
ADDITIONAL BACKGROUND
The following activities are planned to be accomplished under the direction of the Basin
Committee during ILA V:
1. Ongoing project O&M including routine operation and maintenance activities, permit
compliance actions, optimization of Project operations to maximize environmental
benefits, and response to emergency conditions. O&M activities will include but not be
limited to maintenance and operation of constructed structures, maintenance and
replanting of wetland plantings, maintenance and replanting of streamside vegetation,
bank protection activities, maintenance of aquatic habitat structures, preparation and
implementation of emergency action plans, and control of wildlife hazards in the vicinity
of the projects.
2. Capital Replacement and Improvement Activities consisting of minor and major
maintenance in response to ageing and unforeseen circumstances impacting constructed
projects. This may include but is not limited to repairs to the RDF pond spillway and flow
control structures, repairs and/or replacement of the bypass pipe and structure, habitat
structure repair and/or replacement, in-stream sediment management, replacement or
planting of vegetation associated with habitat restoration projects, and weir replacement.
Capital replacement and improvement is also intended to adaptively manage projects to
meet design goals and optimize overall project performance in response to unforeseen
changing of conditions such as modified basin hydrology, physical site changes, climate
change, regulatory changes and unanticipated aquatic habitat stressors.
3. Project monitoring will document compliance with permitting conditions, support O&M,
address any ongoing O&M issues, quantify effectiveness of the projects in meeting
hydrologic and engineering design goals, and serve as the basis for any changes proposed
to the projects as a result of adaptive management. Project monitoring may also include
monitoring and inspection of flow control structures, hydraulic conveyance systems,
arsenic containment cap, vegetation, RDF berms and damn structures, wildlife, aviation
COMMISSION AGENDA Action Item No. 8j Page 4 of 5
December 10, 2024
Template revised June 27, 2019 (Diversity in Contracting).
wildlife hazards and controls, stream flow, wetland fluctuations, groundwater stream
banks, and habitat structures.
4. Invasive vegetation monitoring and control will reduce the spread of harmful species with
the potential to outcompete native plants in areas where stream restoration projects
have been implemented. Nonnative plants will be removed and replaced with native
plants in the Des Moines Creek stream corridor.
5. Education and outreach may be performed to support local stewardship activities for the
purpose of educating community members about aquatic habitat within Des Moines
Creek and restoration activities completed by the Committee. The Committee may
provide resources to non-profit and local watershed or environmental groups for
watershed activities that support Committee goals.
6. A basin needs assessment will continue the evaluation of quality and quantity of habitat
and water quality conditions in Des Moines Creek needed to continue preservation and
protection of aquatic life. New projects may be identified that build upon the Basin Plan
restoration projects already implemented to further the Committee’s commitment to Des
Moines Creek Basin improvement.
7. Ongoing management of an O&M fund to collect and manage funds necessary to pay for
the operation of projects and normal maintenance activities.
8. Ongoing management of a replacement and improvement fund to collect and manage
funds to pay for any required replacements or improvements deemed necessary as a
result of monitoring or adaptive management.
ATTACHMENTS TO THIS REQUEST
(1) Interlocal Agreement V, Des Moines Creek Basin Plan Restoration Projects
(2) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
April 13, 2004, the Commission authorized the Chief Executive Officer to execute Interlocal
Agreement IV with the Cities of Des Moines and SeaTac, King County and Washington
Department of Transportation to implement the Basin Plan, construct a suite of projects
and designate the Port of Seattle as project manager for the Regional Detention Facility.
The cost to the Port was $11,983,000. The agreement was signed by all parties on June
11, 2004.
November 28, 2000, the Commission authorized the Chief Executive Officer to execute an
Interlocal Agreement III between the Port of Seattle, King County, and the Cities of SeaTac
and Des Moines. The Port’s share of the costs was $170,000, which was included in the
2001 operating budget. The agreement was signed July 30, 2001.
February 24, 1998, the Commission authorized execution of Interlocal Agreement II to
prepare a Preliminary Design Report. The Port’s share of the costs was $78,000, funded
by the Airport Development Fund. The agreement was signed by all four jurisdictions on
June 17, 1998.
COMMISSION AGENDA Action Item No. 8j Page 5 of 5
December 10, 2024
Template revised June 27, 2019 (Diversity in Contracting).
January 15, 1997, by Executive approval, the Managing Director of Aviation signed an
amendment to Interlocal Agreement I to include an additional task to develop pilot
projects and continue the program.
October 2, 1995, by Executive approval, Interlocal Agreement I with the Cities of Des Moines
and SeaTac and King County was authorized to prepare a Basin Plan for the Des Moines
Creek. The Port’s share of the costs was $80,000 which was included in the 1995 and 1996
expense budgets. It was signed by all four jurisdictions on January 16, 1996.