Project Risks / Opportunities
6
Mitigation / Implementation PlanImpactProb.DescriptionType
This has been built into the schedule to
mitigate this risk. Order kiosks early to
avoid delays.
HighMed
Market Conditions – Kiosk Delivery. There
is a long lead time associated with kiosks.
Risk
Mitigated this by including it in the project
schedule and cost estimates. HighMed
Existing kiosks may have inadequate
connectivity and may need data cabling
replacement.
Risk
Include and retain sufficient contingency
to address
HighMed
Further unforeseen site
conditions (behind walls) .Possible
hazardous materials and may need
abatement in Zones 2-5
Risk
During design, evaluate biometric
capability and organizational readiness to
adopt this capability.
HighMed
Future proof new kiosks.Opportunity