
COMMISSION AGENDA – Action Item No. 8f Page 2 of 5
Meeting Date: November 12, 2024
Template revised June 27, 2019 (Diversity in Contracting).
Cruise sponsors were able to maximize efficiencies by pursuing a path forward that included
the barge impact restoration scope to the original Pier 66 Fender Rehabilitation project.
Incorporating the additional scope to the original project allowed efficiencies in that the
damaged elements would be fully restored on an expedited timeline while using existing
permits and resources already mobilized during Phase 2 construction (vs. pursuing an
independent capital project to restore damages). In order to capitalize on this opportunity, the
project team worked swiftly to process immediate procurement needs by utilizing the original
construction contingency.
This additional funding request includes construction- and soft costs associated with the barge
impact scope, as well as additional tribal negotiation costs associated with overall project
impacts during the tribal fishery.
JUSTIFICATION
Upon barge impact in November 2023, the Port Engineering team performed a preliminary
visual inspection of the damages incurred at the south end of Pier 66. The preliminary findings
were further investigated, and replacement/rehabilitation methods assessed to restore full
functionality of the impacted area of the pier. The damaged elements and restoration path
forward are as follows:
1. Bull rail concrete damage: perform concrete repairs and recoat.
2. Sheared bollard: no action to replace missing bollard as it was minimally used, per Port
Facilities.
3. Damage to fender assemblies at three southernmost fender panels: replace two of the
three fender panel assemblies impacted.
4. Impact to fender pin piles at three southernmost fender panels: replace pin piles
supporting southernmost two of the three fender panel assemblies impacted.
5. Damaged steel waler on pier: rehabilitate damaged steel elements to restore original
functionality.
This funding request includes additional design fee, staff coordination time, direct construction
cost, sales tax and contingency applicable to restoring damages due to the Pier 66 barge
collision.
Additionally, this request also accommodates tribal negotiation costs associated with overall
project impact during the tribal fishery. The tribal negotiation in this project included
temporary crane mobilization at Bell Harbor Marina during Phase 1 to assist tribal fishing; and
removal of large marine debris impacting tribal fishing offshore of Terminal 46. The marine
debris removed consisted of several creosote-treated piling bound together with cables and a
large concrete mass that posed a consistent snag risk to tribal nets in the past.