COMMISSION AGENDA – Briefing Item No. 11a Page 2 of 3
Meeting Date: October 22, 2024
Template revised September 22, 2016.
Hazardous Materials, Solid Waste,
and Pollution Prevention
Historical Architectural, Archeological,
and Cultural Resources
Land Use
Natural Resources and Energy Supply
Wetlands
Floodplains
Surface Waters
Groundwater
Wild and Scenic Rivers
The Draft EA identified that surface transportation had significant impacts, but these impacts can
be mitigated. There were other impacts identified, however these impacts did not exceed
regulatory or human health standards and do not require any defined action by FAA to reduce,
avoid, or mitigate them. For many of these categories, the Port has incorporated minimization
measures to further reduce impacts. For example, there will be increases in air emissions that do
not exceed the National Ambient Air Quality Standards (i.e., standards that meet human health
requirements). The Port has many programs to minimize air emissions at SEA such as providing
pre-conditioned to aircrafts or efficiencies to the central mechanical plant, both of which
minimize fossil fuel use.
There will be three public meetings in the cities of SeaTac, Burien, and Des Moines on November
13, 14, and 16. These meetings will allow agencies and the public to speak with subject matter
experts and submit comments. Agencies and the public will also have the option to provide
comments during the 45-day public comment period by email, the project website
(www.sampNTPenvironmentalreview.org), and by mail.
The Port will provide a thorough and broad outreach that will include, and is not limited to, local,
BIPOC (Black, Indigenous, and People of Color), and underrepresented communities. This
includes using variety of media outlets, information on the project website, community meetings,
and translating materials into six additional languages.
Once the public comment period closes, the Port and FAA will review and respond to comments
received and these comments will be considered within final NEPA EA. It is expected that the
final NEPA EA will be published in mid-2025.
SCHEDULE
NEPA
October 21, 2024 Draft NEPA EA released for public comment (45-day public
comment period; 30 days is standard)
December 5, 2024 Draft NEPA EA public comment period ends
Quarter 2 2025 NEPA EA Final Document & Issuance of Record of Decision (FAA
issues decision document) + 60-day appeal period
SEPA
Quarter 3 2025 Draft SEPA EIS released for public comment (30-day comment
period [standard]) + comment period ends