PRELIMINARY AGENDA – Port of Seattle Commission Special Meeting of October 22, 2024 Page 2 of 3
Commissioners: Ryan Calkins ■ Sam Cho ■ Fred Felleman ■ Toshiko Hasegawa ■ Hamdi Mohamed Executive Director: Stephen P. Metruck
To contact commissioners: 206-787-3034 For meeting records and information: commission-public-records@portseattle.org 206-787-3210
www.portseattle.org
8. CONSENT AGENDA (consent agenda items are adopted by one motion without discussion)
8a. Approval of Minutes of the Special Meeting – Study Session of October 8, 2024; the Special Meeting of
October 8, 2024; and the Special Meeting of October 15, 2024. (no enclosure)
8b. Authorization for the Executive Director to Procure and Execute Three Professional Services Indefinite
Delivery, Indefinite Quantity Contracts for Consultant Support for Environmental Services for Potential
Environmental Investigations and Remediation Activities in the Amount of $3,000,000 for Each Contract, for
a Total Not-to-Exceed Capacity of $9,000,000. (memo enclosed)
8c. Authorization for the Executive Director to Execute Seven Professional Services Indefinite Delivery, Indefinite
Quantity Contracts for 2025 Professional Design Services Including Architectural Design; Mechanical,
Electrical and Plumbing Design; and Passenger Loading Bridge Design, for a Total Combined Not-to-Exceed
Capacity of $30,000,000. (memo enclosed)
8d. Commission Approval of International Travel Requests for Known Travel in the Fourth Quarter 2024.
(memo enclosed)
8e. Authorization for the Executive Director to Increase the Project Budget by $470,000 for a New Total Project
Cost of $2,220,000, for the SEA Ramp Tower Voice Communication System Project Increase.
(CIP C#801404) (memo enclosed)
8f. Authorization for the Executive Director to Execute a New Collective Bargaining Agreement Between the Port
of Seattle and Teamsters Local 174, Representing Truck Drivers at Both Marine Maintenance and Port
Construction Services, Covering the Period from June 1, 2024, through May 31, 2027.
(memo and agreement enclosed)
8g. Authorization for the Executive Director to Execute agreements for the Continuation of the South King County
Community Impact Fund (SKCCIF) Environmental and Economic Recovery Programs for the Next Five Years
2025-2029 and to Contract up to a Total Amount of $14,000,000. (memo and previous briefing memo
enclosed)
8h. Authorization for the Executive Director to Advertise and Execute a Construction Contract for 2025 Airfield
Projects - Contract 1; to Transfer Budget/Authorization Among the 2025 Airfield Projects; to Transfer
Budget/Authorization for South Concourse Utility Replacement Scope from CIP C#800930 2021-2025 Airfield
Pavement and Supporting Infrastructure to CIP C#801203 South Concourse Evolution; to Procure Long-
Lead Items; to Include a Project Labor Agreement for the Contract; and to Authorize Use of Port Crews for
Abatement Work, in a Requested Amount of $20,850,000 and a Total Estimated Project Cost of
$197,904,000. (memo and presentation enclosed)