
COMMISSION AGENDA – Action Item No. 8h Page 8 of 9
Meeting Date: October 22, 2024
Template revised June 27, 2019 (Diversity in Contracting).
ATTACHMENTS TO THIS REQUEST
(1) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Program (CIP
C800930).
March 12, 2024 – The Commission authorized for the Executive Director to (1) advertise and
execute a construction contract for 2024 Airfield Projects–Contract 2; (2) transfer
budget/authorization, as necessary, between the 2024 Airfield Projects; (3) procure long
lead items; (4) include a Project Labor Agreement for the contract; and (5) authorize use
of Port crews for abatement work.
October 24, 2023 – The Commission authorized for the Executive Director to (1) advertise
and execute a construction contract for 2024 Airfield Projects - Contract 1; (2) transfer
budget/authorization, as necessary, between the 2024 Airfield Projects; (3) transfer
budget/authorization for Gate B11 Passenger Loading Bridge (PLB) civil foundation from
CIP C801180 PLB Phase 3 Project to CIP C800930 2021-2025 Airfield Pavement and
Supporting Infrastructure Replacement Program; (4) procure long lead items; (5) include
a Project Labor Agreement for the contract; and (6) authorize use of Port crews for
abatement work. 2024 Airfield Projects – Contract 1 encompasses federally funded
pavement and utility infrastructure. The amount of this authorization request is
$50,500,000.
October 25, 2022 – The Commission authorized the Executive Director to (1) advertise,
execute two separate construction contracts, and transfer budget/authorization, as
necessary, among the 2023 Airfield Projects; (2) procure long lead items; (3) include a
Project Labor Agreement for both contracts; (4) authorize use of Port crews for
abatement work. The amount of this authorization request is $67,153,000. The total
estimated cost for all projects included in this authorization is $255,945,000.
November 16, 2021 - The Commission authorized the Executive Director to (1) advertise
and execute a major works construction contract and (2) include a Project Labor
Agreement for the 2022 Airfield Pavement and Supporting Infrastructure Replacement
Project, at the Seattle-Tacoma International Airport. This authorization is for
$24,000,000 with a total authorized to date of $79,195,000 and a previously approved
total 2021-2025 program budget of $153,500,000.
August 10, 2021 – The Commission authorized the Executive Director to advertise and
award a major public works contract to replace the North Runway Protection Zone
Culvert (NRPZ Culvert), a year 2022 component of the 2021 to 2025 Airfield Pavement
and Supporting Infrastructure Replacement Program. This construction authorization is
for $3,800,000 for a total program authorization to date of $55,195,000. The total 2021-
2025 program cost is $153,500,000.
November 10, 2020 – The Commission authorized the Executive Director to (1) advertise
and execute a major works construction contract and (2) include a project labor