Template revised January 10, 2019.
COMMISSION
AGENDA MEMORANDUM
Item No. 8h
ACTION ITEM Date of Meeting October 22, 2024
DATE: October 15, 2024
TO: Stephen P. Metruck, Executive Director
FROM: Eileen Francisco, Director Aviation Project Management
Laurel Dunphy, Director Airport Operations
Keri Stephens, Director Aviation Facility and Capital Program
SUBJECT: 2025 Airfield Projects Contract 1 Construction Authorization (CIP# C800930,
C801177 and C801303)
Amount of this request: $20,850,000
Total estimated project cost:
$197,904,000
ACTION REQUESTED
Request Commission authorization for the Executive Director to (1) advertise and execute a
construction contract for 2025 Airfield Projects - Contract 1; (2) transfer budget/authorization
among the 2025 Airfield Projects; (3) transfer budget/authorization for South Concourse utility
replacement scope from CIP C800930 2021-2025 Airfield Pavement and Supporting
Infrastructure to CIP 801203 South Concourse Evolution; (4) procure long lead items; (5) include
a Project Labor Agreement for the contract; and (6) authorize use of Port crews for abatement
work.
2025 Airfield Projects Contract 1 encompasses pavement and utility infrastructure. The
amount of this authorization request is $20,850,000.
EXECUTIVE SUMMARY
This construction contract is comprised of three interdependent Capital Improvement Projects
(CIPs). The details of the authorization and total estimated project cost by CIP are shown
below.
CIP Name/#
Amount of this Request
Total Estimated Project Cost
2021-2025 Airfield Pavement and
Supporting Infrastructure
Replacement Program C800930
$3,726,000 $177,874,000
COMMISSION AGENDA – Action Item No. 8h Page 2 of 9
Meeting Date: October 22, 2024
Template revised June 27, 2019 (Diversity in Contracting).
Airfield Utilities Improvement
C801177
$17,124,000 $20,030,000
Taxiway A Circuit Replacement
C801303
$0 $39,500,000
Total Authorization of this
Request
$20,850,000
The above projects have overlapping work areas and design functionality, interdependent
operational impacts, and share 2025 schedule milestones. As such they were planned,
designed, and phased to be delivered concurrently for purposes of Airfield safety, efficiency,
and minimization of operational impacts.
JUSTIFICATION
The projects being co-delivered via the 2025 Airfield Projects - Contract 1 consist of a variety of
physically and functionally interdependent Capital Improvements designed to renew and
replace failing infrastructure, ensure continued operational safety and security, and meet SEA’s
regulatory requirements. The Taxiway A Circuit Replacement project obtained full Commission
authorization in March 2024 for design and construction. The justification of the two projects
(CIPs) under this authorization request is summarized below:
The 2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Program is an
ongoing program of airfield pavement replacement and is required to provide safe and efficient
conditions for aircraft operations and meet Federal Aviation Administration (FAA)
requirements.
Airfield Utility Improvement (AUI) is an ongoing project to replace aging, failing, and over-
capacity utility systems serving the existing terminal and apron areas.
This request includes authorization to transfer scopes consisting of Industrial Wastewater
System (IWS) and power lines from 2021-2025 Airfield Pavement and Supporting Infrastructure
C800930 to South Concourse Evolution C801203. These scopes are within the work area limits
for the South Concourse Evolution project, and not time sensitive. Including them with the
South Concourse Evolution project will be more efficient and avoid impacting the same gates
twice.
Diversity in Contracting
Through the Diversity in Contracting program, a Women and Minority Business Enterprise
(WMBE) aspirational goal of 12% will be included in the procurement of the construction
contract.
COMMISSION AGENDA – Action Item No. 8h Page 3 of 9
Meeting Date: October 22, 2024
Template revised June 27, 2019 (Diversity in Contracting).
DETAILS
These projects will interface with other projects and airline operations. Continual coordination
with Airport Operations, Airlines, and related Tenants will ensure the least possible operational
impact during construction.
A project labor agreement will be used for these projects based on the importance of labor
continuity and the need to minimize any risk of impact to operations during construction.
Scope of Work
The 2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Program replaces
distressed airfield pavements, joint sealant, and supporting infrastructure at the Airport.
Airfield work under this program in 2025 includes pavement replacement along the South
Concourse Taxilane, around the Q gates and Spot 55, and along Taxiway A; joint sealant
replacement at Taxiway E, G, C, and D; guidance signage replacement; Channel Drain
replacement outside gate A4, and oil water separator installation at the batch plant area.
Project staff will procure long lead items including miscellaneous frames and covers for airfield
utilities.
The AUI project is a three-year project to replace aging, failing, and over-capacity utility systems
serving the existing terminal and apron areas. The 2024 AUI scope is located on the north side
of the South Concourse and Concourse C, including sanitary sewer, domestic power,
communications, and the IWS.
Schedule
Activity
Construction start 2025 Quarter 2
In-use date 2026 Quarter 2
Cost Breakdown This Request Total Project
2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Prog. (C800930)
Design $0 $16,000,000
Construction $3,726,000 $161,874,000
Total $3,726,000 $177,874,000
Airfield Utility Improvements (C801177)
Design $0 $2,905,200
Construction $17,124,000 $17,124,800
Total $17,124,000 $20,030,000
COMMISSION AGENDA – Action Item No. 8h Page 4 of 9
Meeting Date: October 22, 2024
Template revised June 27, 2019 (Diversity in Contracting).
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 Proceed only with Airfield Pavement and Supporting Infrastructure
Replacement Program scope. Do not proceed with the project scope in the Airfield Utility
Improvements which includes sanitary sewer main pipe, power, communication, and the
Industrial Wastewater System (IWS)
Cost Implications: $3,726,000 in Capital Cost for 2025 Airfield Pavement and Supporting
infrastructure Replacement Project.
Pros:
1. Reduced capital spending in 2025.
2. Less construction impacts to airport/airline operations in 2025.
Cons:
1. Risk of a failed sanitary sewer and impacts to Main Terminal and South Concourse
operations.
2. Sewer capacity will not meet current or future needs of the Main Terminal, Concourse
C, and South Concourse.
3. Will cause future operational impacts to repair, replace, or install other utilities in the
same areas.
This is not the recommended alternative.
Alternative 2 – Construct each individual project with separate construction contracts.
Cost Implications: $23,000,000 in Capital Cost to deliver the projects via two major construction
contracts, $2,150,000 more than delivering via one major construction contract as proposed by
the recommended alternative.
Pros:
1. Less complexity for budget tracking during construction.
Cons:
1. Reduced efficiencies due to rework.
2. Additional labor costs for contractor on-boarding and mobilizations, double-project
ramp up and close out.
3. Increased coordination required between overlapping projects.
4. Increased construction safety risk due to overlapping work areas.
5. Additional and recurring impacts to airfield operations until all efforts are completed.
This is not the recommended alternative.
COMMISSION AGENDA – Action Item No. 8h Page 5 of 9
Meeting Date: October 22, 2024
Template revised June 27, 2019 (Diversity in Contracting).
Alternative 3 – Move forward to construct the projects as a single coordinated effort.
Cost Implications: $20,850,000
Pros:
1. Reduces safety risks, minimizes operational impacts and increases efficiencies as
coordination and construction is managed as a single effort.
2. Minimizes time to completion, limiting exposure to future cost increases, while
delivering benefits expeditiously.
3. Programmatic replacement of aged and distressed pavements and related
infrastructures.
Cons:
1. Earlier capital spending in 2025.
This is the recommended alternative.
FINANCIAL IMPLICATIONS
2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Program
(C800930) -
Cost Estimate/Authorization Summary Capital Expense
Total
COST ESTIMATE
Original estimate $155,740,000
$560,000
$156,300,000
Previous changes – net $23,970,000
$0
$23,970,000
Current Change ($2,396,000)
$0
($2,396,000)
Revised estimate $177,314,000
$560,000
$177,874,000
AUTHORIZATION
Previous authorizations $153,546,000
$360,000
$153,906,000
Authorization transferred from C801177 $20,242,000
$0
$20,242,000
Current request for authorization $3,526,000
$200,000
$3,726,000
Total authorizations, including this request $177,314,000
$560,000
$177,874,000
Remaining amount to be authorized $0
$0
$0
COMMISSION AGENDA – Action Item No. 8h Page 6 of 9
Meeting Date: October 22, 2024
Template revised June 27, 2019 (Diversity in Contracting).
Airfield Utility Improvements (C801177) –
Cost Estimate/Authorization Summary Capital
Expense
Total
COST ESTIMATE
Original estimate $34,592,000
$0
$34,592,000
Previous changes – net ($14,562,000)
$0
($14,562,000)
Revised estimate $20,030,000
$0
$20,030,000
AUTHORIZATION
Previous authorizations $23,148,000
$0
$23,148,000
Authorization transferred to C800930 ($20,242,000)
$0
($20,242,000)
Current request for authorization $17,124,000
$0
$17,124,000
Total authorizations, including this request $20,030,000
$0
$20,030,000
Remaining amount to be authorized $0
$0
$0
Annual Budget Status and Source of Funds
2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Program
(CIP C800930)
This project was included in the 2024-2028 capital budget and plan of finance with a
budget of $159,467,559. The capital increase of $17,846,441 was transferred from the
Aeronautical Allowance
1
CIP C800753 resulting in no net change to the Airport capital
budget. This project has a Majority-In-Interest approval from the airlines in January
2020. The funding sources will be the Airport Development Fund, AIP grants, and
revenue bonds. The capital project C800930 receives federal grant funding for eligible
items meeting FAA standards with no anticipated FAA grant reimbursement for the year
2025 and a total of $50,000,000 expected for the life of the program.
AF Utility Improvements (CIP C801177)
This project was included in the 2024-2028 capital budget and plan of finance with a
budget of $40,272,441. The capital decrease of $20,242,441 was transferred to the
Aeronautical Allowance CIP C800753 resulting in no net change to the Airport capital
budget. The funding sources would be the Airport Development Fund and existing
Airport Revenue Bonds.
1
The Aeronautical Allowance is included in the Capital Improvement Plan to ensure funding capacity for
unspecified projects, cost increases for existing projects, new initiatives, and unforeseen needs. This ensures funding
capacity for unanticipated spending within the dollar amount of the Allowance CIP.
COMMISSION AGENDA – Action Item No. 8h Page 7 of 9
Meeting Date: October 22, 2024
Template revised June 27, 2019 (Diversity in Contracting).
Financial Analysis and Summary
C800930 2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Program
Project cost for analysis $177,874,000
Business Unit (BU) Airfield movement and Airfield apron
Effect on business performance
(NOI after depreciation)
NOI after depreciation will increase due to inclusion of
capital (and operating) costs in airline rate base.
IRR/NPV (if relevant) N/A
CPE Impact Total project cost CPE of $0.40 in 2027; annual CPE of
$0.01 in 2027.
C801177 AF Utility Improvements
Project cost for analysis $20,030,000
Business Unit (BU) Airfield movement and airfield apron
Effect on business performance
(NOI after depreciation)
NOI after depreciation will increase due to inclusion of
capital (and operating) costs in airline rate base.
IRR/NPV (if relevant) N/A
CPE Impact $0.06 in 2027
Future Revenues and Expenses (Total cost of ownership)
2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Program (CIP
C800930)
The AIP project will not have an impact on annual Aviation Maintenance Operating and
Maintenance (O&M) costs for the pavement assets. This project may lead to a reduction in the
amount of time currently spent by the Port Maintenance team on joint seal and pavement spall
repairs. After implementing the project, the improved portions of the pavement will have a
renewed 40-year asset life and a greatly reduced risk of the pavement producing loose gravel
and rock Foreign Object Debris (“FOD”) that could be picked up by vehicle tires or blown by jet
engine exhaust and spread across the apron, taxiways and runways.
Airfield Utilities Infrastructure (AUI) (CIP C801177)
The AUI project will not have an impact on annual Aviation Maintenance O&M costs for
mechanical or electrical systems and may lead to a reduction in the amount of time currently
spent by the field crew on pipe inspections due to the current condition of the water and sewer
systems. After implementing the project, the improved portions of the water and sewer
systems will have a renewed 50-year asset life and a greatly reduced risk of failures, emergency
repair and maintenance work, and impacts to operations.
COMMISSION AGENDA – Action Item No. 8h Page 8 of 9
Meeting Date: October 22, 2024
Template revised June 27, 2019 (Diversity in Contracting).
ATTACHMENTS TO THIS REQUEST
(1) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Program (CIP
C800930).
March 12, 2024 – The Commission authorized for the Executive Director to (1) advertise and
execute a construction contract for 2024 Airfield Projects–Contract 2; (2) transfer
budget/authorization, as necessary, between the 2024 Airfield Projects; (3) procure long
lead items; (4) include a Project Labor Agreement for the contract; and (5) authorize use
of Port crews for abatement work.
October 24, 2023 The Commission authorized for the Executive Director to (1) advertise
and execute a construction contract for 2024 Airfield Projects - Contract 1; (2) transfer
budget/authorization, as necessary, between the 2024 Airfield Projects; (3) transfer
budget/authorization for Gate B11 Passenger Loading Bridge (PLB) civil foundation from
CIP C801180 PLB Phase 3 Project to CIP C800930 2021-2025 Airfield Pavement and
Supporting Infrastructure Replacement Program; (4) procure long lead items; (5) include
a Project Labor Agreement for the contract; and (6) authorize use of Port crews for
abatement work. 2024 Airfield Projects – Contract 1 encompasses federally funded
pavement and utility infrastructure. The amount of this authorization request is
$50,500,000.
October 25, 2022 – The Commission authorized the Executive Director to (1) advertise,
execute two separate construction contracts, and transfer budget/authorization, as
necessary, among the 2023 Airfield Projects; (2) procure long lead items; (3) include a
Project Labor Agreement for both contracts; (4) authorize use of Port crews for
abatement work. The amount of this authorization request is $67,153,000. The total
estimated cost for all projects included in this authorization is $255,945,000.
November 16, 2021 - The Commission authorized the Executive Director to (1) advertise
and execute a major works construction contract and (2) include a Project Labor
Agreement for the 2022 Airfield Pavement and Supporting Infrastructure Replacement
Project, at the Seattle-Tacoma International Airport. This authorization is for
$24,000,000 with a total authorized to date of $79,195,000 and a previously approved
total 2021-2025 program budget of $153,500,000.
August 10, 2021 – The Commission authorized the Executive Director to advertise and
award a major public works contract to replace the North Runway Protection Zone
Culvert (NRPZ Culvert), a year 2022 component of the 2021 to 2025 Airfield Pavement
and Supporting Infrastructure Replacement Program. This construction authorization is
for $3,800,000 for a total program authorization to date of $55,195,000. The total 2021-
2025 program cost is $153,500,000.
November 10, 2020 The Commission authorized the Executive Director to (1) advertise
and execute a major works construction contract and (2) include a project labor
COMMISSION AGENDA – Action Item No. 8h Page 9 of 9
Meeting Date: October 22, 2024
Template revised June 27, 2019 (Diversity in Contracting).
agreement for the replacement of distressed pavements and supporting infrastructure
for the 2021 portion of the 2021-2025 Airfield Pavement and Supporting Infrastructure
Replacement Program at the Seattle-Tacoma International Airport. This construction
authorization is for $37,900,000 for a total authorization to date of $51,395,000. The
total 2021-2025 program cost is $153,500,000.
October 22, 2019 The Commission authorized the Executive Director to authorize design
and preparation of construction documents for the 2021-2025 Airfield Pavement and
Supporting Infrastructure Replacement Projects at the Seattle-Tacoma International
Airport in the amount of $16,000,000 and approve the use of a project labor agreement
(PLA) for each year’s construction contract.
Airfield Utilities Infrastructure (AUI) (CIP C801177)
October 24, 2023 The Commission authorized for the Executive Director to (1) advertise
and execute a construction contract for 2024 Airfield Projects - Contract 1; (2) transfer
budget/authorization, as necessary, between the 2024 Airfield Projects; (3) transfer
budget/authorization for Gate B11 Passenger Loading Bridge (PLB) civil foundation from
CIP C801180 PLB Phase 3 Project to CIP C800930 2021-2025 Airfield Pavement and
Supporting Infrastructure Replacement Program; (4) procure long lead items; (5) include
a Project Labor Agreement for the contract; and (6) authorize use of Port crews for
abatement work. 2024 Airfield Projects – Contract 1 encompasses federally funded
pavement and utility infrastructure. The amount of this authorization request is
$50,500,000.
October 25, 2022 – The Commission authorized the Executive Director to (1) advertise,
execute two separate construction contracts, and transfer budget/authorization, as
necessary, among the 2023 Airfield Projects; (2) procure long lead items; (3) include a
Project Labor Agreement for both contracts; (4) authorize use of Port crews for
abatement work. The amount of this authorization request is $67,153,000. The total
estimated cost for all projects included in this authorization is $255,945,000.
August 10, 2021 – The Commission authorized the Executive Director to (1) complete design
and prepare construction documents for the Airfield Utilities Infrastructure (AUI) project
at Seattle-Tacoma International Airport (SEA) and (2) enter into reimbursable
agreements with the Federal Aviation Administration. This design authorization is for an
amount of $6,300,000 out of a total estimated project cost of $46,200,000.
Taxiway A Recircuiting (CIP C801177)
March 26, 2024 The Commission authorized for the Executive Director to (1) authorize
final design and preparation of construction bid documents; (2) advertise, award, and
execute a major public works construction contract; (3) procure long lead material
items; (4) include a Project Labor Agreement for the contract; (5) authorize use of Port
crews for abatement work for Taxiway A Circuit Replacement project at Seattle-Tacoma
International Airport.