PrimaryFireStationFullConstruction
Authorization(CIP#C801256)
September24,2024
ItemNo.8c_ supp
MeetingDate:September 24,2024
2
ProjectOverview
ProjecttoaddressStation1improvements neededtosupportcontinuingoperationaluseof
existingfacility untilit isdisplacedbyfuturedevelopment
Priorities
1. Addressstationmechanicalsystemperformance,airquality,andtemperaturecontrol
2. Improvedormitoryaccommodations
a) Airquality(circulation)
b) Bunkprivacy
c) Responselightingvstaskandambient
d) Internet/Wi‐Fiaccess
3
PrimaryFireStation(Station1)
N
4
ProjectProgram
Enablingwork–Previouslyauthorized
• UseNorthapparatusbaytohousetwoconstructiontrailersfortemporarydormitoryuse.
Mechanicalwork
• Replacetwoair‐handlingunits(AHU’s )thatareinefficientandpasttheirusefullife
• Replacekitchenrangeandexhausthoodthatarenotfunctioningandpartofthe
mechanicalsystemupgrades.
Electricalwork
• Replacetransformerandupgradeexistingsystemtosupportnewmechanicalsystem
Dormitorywork
• Renovateexistingdormstoprovidebetterairquality,privacyandnoisereduction
• Extenddatainfrastructureforinternetandwifi accesspoints.
• Upgradecomputerautomateddispatch/alarmnotificationforunitcall‐out(CAD‐
RMS/FSA)toimprovenotificationsbased
onresponsetypeneeded.
AreaofWork–EastandWestDorms
5
EastDormView
WestDormView
AreaofWork– DiningandKitchenArea
6
InteriorViewofNewR oofandDiningArea
ExteriorViewofNewRoofandOutdoorPatio
TargetProjectSchedule
7
• MilestoneDates:
• CompleteFinalDesign–Q32024
• CommissionConstructionAuthorizationEarlyWorkPackage–May2024
• CommissionConstructionAuthorizationMaximumAllowableConstructionCost
(MACC)Q3‐2024
• BidOpening–Q32024
• NoticetoProceed–Q42024
• SubstantialCompletion–Q22026
8
ActionRequested
RequestCommissionauthorizationfortheExecutiveDirectorto:
(1) AuthorizefullconstructionworkforthePrimaryFireStationContinuingOperations
Preservation
(2) Requestprojectauthorizationforfullbudgetamountof$29,922,000.
Questions
9