Template revised January 10, 2019.
COMMISSION
AGENDA MEMORANDUM
Item No.
8j
ACTION ITEM
Date of Meeting
August 13, 2024
DATE: August 2, 2024
TO: Stephen P. Metruck, Executive Director
FROM: Karlina Smith, Senior Manager Recreational Boating
Julie Yun, Waterfront Capital Project Manager
SUBJECT: Shilshole Bay Marina X-Dock Rehabilitation Additional Funds Request
(CIP# C800570)
Amount of this request:
$650,000
Total estimated project cost:
$2,300,000
ACTION REQUESTED
Request Commission authorization for the Executive Director to approve additional funding to
award and execute a major public works contract and proceed with construction. Total request
for this action is $650,000 for a project total authorization of $2,300,000.
EXECUTIVE SUMMARY
Shilshole Bay Marina serves a broad range of recreational boating customers including moorage
tenants, a liveaboard community, youth sailing education, dry boat storage and the public. The
X Dock facility at Shilshole Bay Marina is located adjacent to the dry boat storage yard and
consists of a fixed pier supported by timber piles, two vessel hoists (“jib cranes”) for launching
vessels, a gangway, and a floating dock structure. This project will remove the 20 deteriorated
creosote-treated timber piles currently supporting the fixed pier and replace them with 13 steel
piles.
In May 2022, the Port Commission authorized the advertisement and award of a construction
contract for the SBM Dock X Pile Rehabilitation project. Since then, staff has completed the
design and received full permit approval and tribal concurrence from the Suquamish and
Muckleshoot tribes. The major works contract was advertised and bid opening occurred on July
2, 2024.
One bid was received in response to the construction advertisement and acceptance of the bid
would exceed the previously authorized total project budget of $1,650,000. The bid received
was from Quigg Bros., Inc. for a total of $908,000, which is $448,000 or 97% in exceedance of
the Engineer’s Estimate of $460,000. This overage can be attributed to the saturation of marine
COMMISSION AGENDA Action Item No. 8j Page 2 of 6
Meeting Date: August 13, 2024
Template revised June 27, 2019 (Diversity in Contracting).
construction work and finite construction labor and rental equipment resources in the current
market, as well as the increased market rates for steel fabrication and materials.
The additional funds requested in this action will be used to cover the difference of the bid
amount, associated Washington state sales tax, project contingency, Port-managed marine
mammal and murrelet monitoring, and compounded soft costs incurred since 2022 from delay
caused by longer than anticipated permitting timeline.
The recommendation is to accept the single bid received from Quigg Bros., Inc. Their bid has
been reviewed and confirmed responsible.
JUSTIFICATION
The current fixed pier structure is supported by the original 20 creosote timber piles which are
now reaching the end of their service life. Several have been previously repaired or show
section loss and advanced deterioration. By replacing this support system with 13 steel piles,
we will reduce the total number of piles, improve environmental conditions, and provide a
significantly increased service life of over 30 years. The current superstructure and decking are
in good condition and will be retained to utilize its full-service life. The supporting structure has
been designed to be compatible with the eventual rehabilitation of the superstructure.
This capital project has a history of delay since the original timeline for construction in the
2022-2023 in-water work window. Reasons for delay include Port staff resource constraints and
permitting delay (SDCI Construction Permit issued Q4 2022 and the Port’s Pile Systems Repair &
Maintenance Programmatic permit that was renewed in Q4 2023). Per Port Engineering, the
current condition of this facility is in a severely deteriorated and hollowed state in many
locations on the existing timber piles. The pile rehabilitation construction is recommended to
be executed as soon as possible, and load restricted operation is recommended leading up to
construction completion to maintain structural condition and protect public safety.
The current market condition in the marine construction industry trends toward increased
competition and accompanying escalation. As such, there is limited opportunity for ensuring an
improved outcome in the case of re-advertisement.
Construction will be executed from the waterside as much as practicable to avoid construction
impacts to the surrounding businesses and public recreational activities. The construction
timeline has been phased to mitigate impacts to seasonal recreational boating events (including
the 2024 J/24 World Championships).
Full permitting approval has been received for the 2024-2025 in-water work window proposed
for this construction scope. Both Muckleshoot and Suquamish tribes have provided tribal
concurrence as a condition of the Port’s Pile Programmatic Permit. In lieu of the dedicated
tribal crane at SBM Dock A being out of order, Port staff are in coordination with the tribes on
use of an alternate crane during the tribal fishery. The completion of this pile rehabilitation
COMMISSION AGENDA Action Item No. 8j Page 3 of 6
Meeting Date: August 13, 2024
Template revised June 27, 2019 (Diversity in Contracting).
project will restore full operational capability at SBM Dock X, and avail an additional option for
interim use during the tribal fishery until the dedicated tribal crane is back in service.
Diversity in Contracting
There is a 10% aspirational goal for WMBE utilization for the construction contract. The nature
of this work lends itself to limited scope opportunities, as this work is likely to be performed
entirely by the general contractor. The single bid received has not met this aspirational goal.
However, they have provided documentation indicating their affirmative efforts to achieve the
goal. Project staff will be working with the Diversity in Contracting Department throughout
construction to further evaluate WMBE opportunities as they arise.
DETAILS
Scope of Work
This project will replace the 20 existing creosote timber support piles with 13 galvanized steel
piles and frame system to support the existing wooden superstructure.
Schedule
This project is currently fully permitted for a work window from October 2024 February 2025.
Full concurrence from both Muckleshoot and Suquamish tribes has been received as a
condition of the Port’s Pile Programmatic permit.
The history of project delays in this project are as follows:
- 8/21/2021: Project delayed to target the next fish window in 2022/2023 due to SDCI
permitting review backlog and Port staff resource constraints.
- 8/25/2022: Advertisement delayed to target the next fish window in 2023/2024 due to
protracted SDCI construction permit negotiations resulting in permit delay.
- 6/21/2023: Advertisement delayed to target the next fish window in 2024/2025 due to
Pile Programmatic Permit renewal delay.
Activity
Commission design authorization
Commission construction authorization
Commission additional funds authorization
Construction Start
In-use date
COMMISSION AGENDA Action Item No. 8j Page 4 of 6
Meeting Date: August 13, 2024
Template revised June 27, 2019 (Diversity in Contracting).
Cost Breakdown
This Request
Total Project
Design
$50,000
Construction
$600,000
Total
$650,000
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1No additional funding and re-advertise contract.
Cost Implications: No cost implication to this option.
Pros:
(1) Low potential for improved bid outcome. There is no tangible market indication or
strategy identified to ensure an improved bid outcome in the case of future re-
advertisement.
Cons:
(1) Schedule delay by at least one work window, due to need for repackaged work scope
and corresponding soft costs.
(2) Structural failure risk due to continued deterioration.
(3) Operational impact due to load restriction imposed to mitigate continued
deterioration and safety risk.
(4) Potential for permit resubmittal (if altered scope) and/or renewal; tribal concurrence
would be renegotiated with new scope and construction dates
(5) Financial risk due to escalation and market trends toward competitive marine
construction environment.
This is not the recommended alternative.
Alternative 2Proceed with approval of additional funds and accept current bid proposal.
Cost Implications: Allocation of additional $650,000 in the Capital Plan.
Pros:
(1) Maintain current project schedule for construction in 2024-2025 permitting in-water
work window.
(2) Ensure asset preservation and restore structural integrity.
(3) Restore facility operation with no load restriction on recreational boating customer
use.
(4) Avoid cost escalation from increasingly competitive market trends in marine
construction industry.
(5) Create additional option for temporary tribal crane while dedicated tribal crane at
SBM Dock A is out of service.
COMMISSION AGENDA Action Item No. 8j Page 5 of 6
Meeting Date: August 13, 2024
Template revised June 27, 2019 (Diversity in Contracting).
Cons:
(1) Allocate $650,000 in additional capital funds to proceed with bid acceptance and
construction.
This is the recommended alternative.
FINANCIAL IMPLICATIONS
Cost Estimate/Authorization Summary
Capital
Expense
Total
COST ESTIMATE
Original estimate
$1,670,000
$0
$1,670,000
Previous changes net
-$20,000
0
-$20,000
Current change
$650,000
0
$650,000
Revised estimate
$2,300,000
0
$2,300,000
AUTHORIZATION
Previous authorizations
$1,650,000
0
$1,650,000
Current request for authorization
$650,000
0
$650,000
Total authorizations, including this request
$2,300,000
0
$2,300,000
Remaining amount to be authorized
$0
$0
$0
Annual Budget Status and Source of Funds
This project is included in the 2025 Capital Plan under C800570 SBM Dock X Pier Replacement
with a total project cost of $1,650,000. The additional cost of this project will be offset by the
Maritime Capital Reserve C800002.
This project will be funded by the General Fund.
Financial Analysis and Summary
Project cost for analysis
$2,300,000
Business Unit (BU)
Shilshole Bay Marina
Effect on business performance
(NOI after depreciation)
This project is an enhancement project to the SBM; it won't
create additional revenue. Depreciation will increase by
$115,000 per year for 20 years
IRR/NPV (if relevant)
The NPV is the present value of the project cost.
CPE Impact
N/A
Future Revenues and Expenses (Total cost of ownership)
Extending the useful service life of our existing assets defers eventual replacement costs for a
longer period, supporting the economic vitality of our operations. Other economic benefits
include cost effectiveness and minimum disruption to the terminal operations.
COMMISSION AGENDA Action Item No. 8j Page 6 of 6
Meeting Date: August 13, 2024
Template revised June 27, 2019 (Diversity in Contracting).
ATTACHMENTS TO THIS REQUEST
(1) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
May 10, 2022 The Commission approved construction authorization in the amount of
$1,200,000 for Shilshole Bay Marina X-Dock Rehabilitation.
January 26, 2021 The Commission approved design authorization in the amount of
$450,000 for Shilshole Bay Marina X-Dock Rehabilitation.