Sanitary Pipe Replacement
Abhinav Prasad
Project Manager, AV-PMG
Item No. 8d_supp
Meeting Date: August 13, 2024
Project Scope
Replace failing sanitary piping in three locations:
2
Concourse A
Main Terminal
Central Terminal North
Failed Piping and Space Constraints
3
Cracked/corroded pipe from 2020
Mechanical Room 4 (STS Level) Under Central Terminal (STS Level)
Schedule
4
Milestone Date
Design Complete Q2 - 2024
Commission Authorization for Construction Q3 - 2024
Construction Award Q4 - 2024
Substantial Completion Q2 - 2026
Project Budget
5
Authorization Capital Expense Total
Previous authorizations $650,000 $0 $650,000
Current request for authorization $2,635,000 $65,000 $2,700,000
Total authorizations, including this request $3,285,000 $65,000 $3,350,000
Remaining amount to be authorized $0 $0 $0
Cone of Certainty
We
Are
Here
6
Action Requested
Advertise, award, and execute a major works construction contract.
Execute related project change orders, amendments, work authorizations, purchases, contracts, and
take other actions necessary to support and deliver the Sanitary Pipe Replacement project within the
approved budget .
Utilize Port of Seattle crews, and small and major works on-call contracts, to support construction
activities.
Increase project budget by $350,000 for a new total budget of $3,350,000.
Request to authorize $2,700,000 for construction services.
Estimated total project cost not to exceed $3,350,000.