CIP: C801234
Budget: $200,000,000 - $300,000,000
Previous Authorization: $13,635,000
Current Request: $6,500,000
Key Schedule Milestones:
• 30% Design Kickoff: August 2024
• 30% Design Complete: April 2025
• Full Design Authorization: 2Q 2025
• Construction Authorization: Q2 2026
• Construction Start: Q3 2026
• In-Use Date: Q4 2028
Project Budget & Schedule