COMMISSION AGENDA – Action Item No. 8f   Page 2 of 6 
Meeting Date: May 28, 2024 
 
Template revised June 27, 2019 (Diversity in Contracting). 
have been in operation in the existing fire station for decades. These systems are outdated or at 
the end of their useful life.  The project team will return in October 2024 to request construction 
authorization for the remaining scope of work.  
 
The amount of this request is $6,700,000 for enabling construction work and the procurement 
of long lead items.   
 
JUSTIFICATION  
Construction  authorization  for  the  enabling  work  is  required  to  provide  temporary  sleeping 
quarters for the fire fighters in the North apparatus bay which will allow for the full program work 
to begin sooner.  The fire fighters will be relocated temporarily into two construction trailers that 
will be modified into sleeping units like their current sleeping unit.  This will allow the station to 
maintain daily operations while construction of the new dormitories is in progress.  
 
This fire station, also known as Station 1, is strategically located to provide the best response to 
airfield and terminal incidents with immediate access to the airfield operations area (AOA) and 
the airport landside roadways.  Sequencing and phasing of the full program work is vital to allow 
for ongoing operations during construction.   
 
To  minimize  disruption  to  the  fire  station,  the  team  has  researched  multiple  scenarios  to 
determine which areas of the station can be under construction while allowing the fire fighters 
access to their daily needs.  Moving the fire fighters into their temporary sleeping quarters will 
allow construction of both East and West side dormitories to occur in the same phase.    
 
Diversity in Contracting 
This project has contracted design and engineering services using an existing  2018 Indefinite 
Delivery Indefinite Quantity (IDIQ) contract with a Small Business requirement of 5%.  To date, 
this design effort has achieved 18% participation.  
Looking forward, working with the Port’s Diversity in Contracting team, the GC/CM construction 
contract WMBE participation aspirational goal has been set at 10%.   
 
DETAILS 
The intent of this project is to replace the existing HVAC systems, including the existing kitchen 
range and dedicated exhaust, to provide needed utility and modern temperature controls that 
the existing systems are no longer capable of delivering.  During the summer months, spaces such 
as the dining area with the solarium roof become very hot and the HVAC system is not capable 
of cooling the space.   
 
In  conjunction  with  the  HVAC  and  utility  upgrades  and  to  meet  current  energy  code 
requirements, the solarium roof will be modified to a solid roof with skylights.  This will reduce 
the heat gain in this area and provide better temperature control in the dining and kitchen areas.