COMMISSION AGENDA – Action Item No. 8f Page 2 of 6
Meeting Date: May 28, 2024
Template revised June 27, 2019 (Diversity in Contracting).
have been in operation in the existing fire station for decades. These systems are outdated or at
the end of their useful life. The project team will return in October 2024 to request construction
authorization for the remaining scope of work.
The amount of this request is $6,700,000 for enabling construction work and the procurement
of long lead items.
JUSTIFICATION
Construction authorization for the enabling work is required to provide temporary sleeping
quarters for the fire fighters in the North apparatus bay which will allow for the full program work
to begin sooner. The fire fighters will be relocated temporarily into two construction trailers that
will be modified into sleeping units like their current sleeping unit. This will allow the station to
maintain daily operations while construction of the new dormitories is in progress.
This fire station, also known as Station 1, is strategically located to provide the best response to
airfield and terminal incidents with immediate access to the airfield operations area (AOA) and
the airport landside roadways. Sequencing and phasing of the full program work is vital to allow
for ongoing operations during construction.
To minimize disruption to the fire station, the team has researched multiple scenarios to
determine which areas of the station can be under construction while allowing the fire fighters
access to their daily needs. Moving the fire fighters into their temporary sleeping quarters will
allow construction of both East and West side dormitories to occur in the same phase.
Diversity in Contracting
This project has contracted design and engineering services using an existing 2018 Indefinite
Delivery Indefinite Quantity (IDIQ) contract with a Small Business requirement of 5%. To date,
this design effort has achieved 18% participation.
Looking forward, working with the Port’s Diversity in Contracting team, the GC/CM construction
contract WMBE participation aspirational goal has been set at 10%.
DETAILS
The intent of this project is to replace the existing HVAC systems, including the existing kitchen
range and dedicated exhaust, to provide needed utility and modern temperature controls that
the existing systems are no longer capable of delivering. During the summer months, spaces such
as the dining area with the solarium roof become very hot and the HVAC system is not capable
of cooling the space.
In conjunction with the HVAC and utility upgrades and to meet current energy code
requirements, the solarium roof will be modified to a solid roof with skylights. This will reduce
the heat gain in this area and provide better temperature control in the dining and kitchen areas.