C800539: Bell Harbor Marina Pile Wrap & Cathodic Protection
C800517: Pier 66 Breakwater Cathodic Protection
Linda Springmann, Director, Cruise and Maritime Marketing
Karlina Smith, Sr. Manager, Recreational Boating
Julie Yun, WPM Capital Project Manager
Item No.: 8c_Supp
Meeting Date: May 28, 2024
Action Requested
Request Commission Authorization from the Executive Director to:
Request Commission authorization for the Executive Director to advertise
and execute a major public works construction contract for the
completion of the Corrosion Protection projects at Bell Harbor Marina
and Pier 66 (CIP# C800539 and C800517). This request is in the amount of
$5,900,000 ($2,500,000 for C800539 BHM / $3,400,000 for C800517 P66)
for a total estimated project cost of $7,095,000 ($3,145,000 for C800539
BHM / $3,950,000 for C800517 P66).
2
Project Overview
3
P66/BHM
Project Area
Existing Condition
4
Corrosion and marine growth on battered piles
with no pile wrap
Typical anode with approximately 70% depletion
5
Project Scope & Coordination
Project Scope:
Pile Wrap at (92) steel piles at the south
apron
Cathodic Protection Anode Replacement
at (498) steel piles at BHM and Pier 66.
Coordination:
Permit approved in-water work window
with requested extension
Avoid tribal fishery
Facility operations (cruise season, rec
boating events schedule)
Simultaneous projects
Project Info
6
Cost Breakdown This Request Total Project
C800539 (BHM) C800517 (P66) C800539 (BHM) C800517 (P66)
Design $0 $0 $645,000 $550,000
Construction $2,500,000 $3,400,000 $2,500,000 $3,400,000
Total - per project $2,500,000 $3,400,000 $3,145,000 $3,950,000
Total - both projects $5,900,000 $7,095,000
Project Timeline
7
Activity Date
Construction Authorization 5/28/2024
Advertise Contract Q4 2024
NTP Q1 2025
Construction Start Q4 2025
In-use date Q2 2026
Questions?
8