COMMISSION AGENDA – Briefing Item No. 10b Page 4 of 5
Meeting Date: May 28, 2024
Template revised September 22, 2016.
• August 8, 2023 – Commission authorized $27,415,000 construction funding for the
construction of the Maritime Innovation Center (C801084, U00414) and Public Site
Improvements (C801211, U00320).
• November 11, 2022 – Commission authorized an additional $500,000 in design funding
for the proposed Fishermen’s Terminal Maritime Innovation Center (C801084, U00414)
to complete design and permitting due to a design error that required correction.
• March 08, 2022 –Commission authorization for the Executive Director to invest at least
$5,718,840 into the Maritime Innovation Center (MInC) to provide required matching
funds for a United States Economic Development Administration grant in the amount of
$5,000,000.
• May 11, 2021 – Commission authorized an additional $1,000,000 in design funding for the
proposed Fishermen’s Terminal Maritime Innovation Center (C801084, U00414) to
complete design and permitting; and (2) to execute an amendment to the existing service
agreement with Miller Hull Partnership, LLP for Fishermen’s Terminal Phased Design
Services in the amount of $2,500,000; for a new Not-To-Exceed (NTE) value of $6,000,000.
• March 23, 2021 – Commission authorized Design and Permitting completion of the FT Site
Improvements (U00320) Under the New CIP C801211, utilizing $1,525,505 in formerly
authorized funding for the Gateway Building.
• December 8, 2020 – Commission authorized Construction of the MInC as the condition
for executing the Interagency Agreement with Washington State Department of
Commerce to allow the acceptance of a $5M grant towards its construction.
• May 14, 2019 – Commission authorized $1,850,000 design funding and an amendment to
the Fishermen’s Terminal Phased Design Services contract, with Miller Hull Partnership
LLP, for $1,000,000 for final planning, design, and permitting for the Maritime Innovation
Center.
• January 22, 2019 – The Commission authorized an additional $1,800,000 in design funding
for FT Gateway Building improvements, and the execution of an amendment to the
existing Architectural/Engineering Services contract for FT Redevelopment for $1,000,000
to complete the final planning, design and permitting of the Gateway Building and FT Site
Improvements.
• January 8, 2019 – Commission received a briefing regarding Maritime Blue Plan and the
Maritime Innovation Center.
• September 26, 2017 – The Commission authorized $1,325,000 construction funding for
the demolition of the existing bank building and Net Sheds 7 and 8. This work has
not yet been advertised for bids, per direction by the Commission, pending finalization of
a Gateway Building tenant lease agreement.
• December 13, 2016 –Commission authorized an initial $3,000,000 for the Fishermen’s
Terminal Redevelopment program planning and design; the total preliminarily estimated
design cost was $7,000,000.
• May 17, 2016 - Commission received a briefing on the planning strategies comprising the
Fishermen’s Terminal Long-Term Strategic Plan.
• October 27, 2015 - Commission received a briefing about the progress of the stakeholder
outreach program for the Fishermen’s Terminal Long-Term Strategic Plan.