Scope of Work
1. Increase contracting authority to fulfill the remaining work to support until
February 2025.
2. Advertise, award, and execute five-year Airport-Wide Window Cleaning service
contract through a competitive process in Q3 2024 and begin a new service in
March 2025.
3. New facilities, North Main Terminal Renovation, Concourse A Building Expansion,
Concourse C expansion, Fire Station, and South Satellite Evolution Renovation,
will be added to the scope as they become online in the next few years.
4. 35% Women- and Minority- Business Enterprise (WMBE) aspirational goals for
contracted work.
5. Incorporating Labor Harmony language into the RFP for the service contract.