Access Control in Communication Rooms
Sharon Miick
Project Manager, AV-PMG
Item No. 8e_supp
Meeting Date: May 14, 2024
Background
• Updated standards for Communication Room security adopted
in 2018.
• Project scope is based on a 2018 internal audit driven by Port
Internal Audit department and the audit’s findings.
• This project addresses communication rooms that are pre-
2018 standard and brings them up to current Port standards.
2
Project Scope
3
• Installation of infrastructure equipment, access
control devices, and surveillance equipment.
• Connection to current STIA Access Control
System and surveillance system.
• Set-up and removal of barricades for securing
the rooms during construction.
Authorizations and Milestones
Milestone Date
Design Complete Q2 2024
Construction Start Q3 2024
In-Use Date Q4 2025
4
Authorizations Project Authorization
Previous authorization (Design) $2,100,000
Total authorized amount (Including this request) $8,100,000
Remaining to be authorized $0
We are here
Cone of Certainty
QUESTIONS?