exceed 60 calendar days’ time extensions, and 3) include a Project Labor Agreement
(PLA) for Phase 3.
• July 26, 2022 – Request Commission authorization for the Executive Director to: (1)
execute an agreement with the Transportation Security Administrative (TSA) to
provide clear access to screening equipment for Phase 2, (2) authorize $34,215,000
for Phase 3 to complete pre-construction services, (3) utilize, advertise, and execute
a General Contractor/Construction Manager (GC/CM) for Phase 3, (4) advertise and
execute a project specific Construction Management (CM) and Airline Technical
Representative (ATR) contract for Phase 3, (5) amend Service Agreement (SA) P-
00317641 to add $18,340,000 for a total contract value of $49,500,000 to complete
design services and provide construction support for Phase 3, and (6) utilize Port
crews for Phase 3 activities, for Baggage Optimization Project at Seattle-Tacoma
International Airport. The total amount of this request is $34,215,000.
• April 19, 2022 – Baggage Optimization Program Update – Quarter 2, 2022.
• January 28, 2020 – Commission Authorization to: (1) execute a construction contract
with the low responsive and responsible bidder for the Baggage Optimization Phase 2
Project at Seattle-Tacoma International Airport, notwithstanding the low bid
exceeding the estimate at time of bid by more than 10 percent, and (2) authorize an
additional $190,737,800 for Phase 2 construction and Phase 3 design for a total
program authorization of $540,050,000.
• April 23, 2019 – Commission Authorization to: (1) advertise, award, and execute a
construction contract for the Baggage Optimization Phase 2 project at Seattle-Tacoma
International Airport; (2) employ a project labor agreement (PLA); and (3) utilize Port
crews and small works contracts to perform construction work.
• February 26, 2019 – Baggage Optimization Quarter 4 Project Briefing.
• October 23, 2018 – Baggage Optimization Quarter 3 Project Briefing.
• June 12, 2018 – Baggage Optimization Quarter 2 Project Briefing.
• January 9, 2018 – Baggage Optimization Quarter 4 Project Briefing.
• September 26, 2017 – Baggage Optimization Quarter 3 Project Briefing.
• June 27, 2017 – Commission authorization to (1) authorize additional design and
project management funds to expand the capacity to 60 million annual passengers
(MAP); (2) use Port crews and small works contracts to perform additional
construction work; and (3) amend Service Agreement P-00317641 to add
$10,160,000.
• October 25, 2016 – Baggage Optimization Quarter 4 Project Briefing.
• July 12, 2016 – Commission authorization to advertise and execute a contract for
Construction Phase 1.
• June 28, 2016– Baggage Program Briefing.
• May 17, 2016 – Checked Baggage Optimization Project Briefing.
• March 8, 2016 – Commission authorization for the Chief Executive Officer to amend
the Baggage Optimization Design Services contract.
• June 23, 2015 – Checked Baggage Optimization Project Briefing.