Risks
5
Risk Impact Probability Mitigation Plan
Lead Time to Delivery:
16 weeks - Fiber optic cables
12 weeks - Wireless equipment
This is the current lead time to delivery expected
as of Q2, 2023. It is expected to go down as the
project progresses towards construction.
CIBS communication rooms are not 2-hour
fire rated.
DAS project is not expected to bring comm rooms
to 2-hr fire rating. Coordinate with AV F&I and
POSFD on this risk as the project progresses. AV
F&I and POSFD are working on a solution to make
all comm rooms to be 2-hr fire rated for
continuous fire rating.
= Low= Medium
= High