
COMMISSION AGENDA – Action Item No. __10c__ Page 2 of 7
Meeting Date: March 26, 2024
Template revised June 27, 2019 (Diversity in Contracting).
beverage services. This will allow the operators to determine whether their concept might thrive
in the airport environment without having to make a significant capital investment and commit
to longer lease terms. Both locations will be designed, constructed, and maintained by the Port.
These units will provide the Port with additional non-aeronautical revenue but are primarily
intended to provide opportunities for small businesses to enter the airport food and beverage
market who otherwise would not be able to due to high build-out and start-up costs.
This program is an extension of the widely successful retail kiosk program, which has advanced
multiple small businesses from introductory kiosk opportunities into both intermediate kiosks
and successful RFP respondents for long-term inline spaces.
Between August 2019 and November 2020, $1,200,000 was authorized for planning and design
services. Originally the total project value was estimated at $5,500,000.
Design solicitation and preliminary concept development occurred between April 2021 and
August 2022. After a slight delay, due to COVID, the project kicked off full design in January 2023.
Upon receiving the 100% design submittal in October 2023, critical design issues arose
concerning the approval to reuse the existing kitchen equipment within the CB-04 location.
Design revisions and extensive coordination was required to secure said approval. Delivering the
space with a diminished cookline or fully replacing the gently used equipment would have been
detrimental to both the project vision and budget. These efforts significantly depleted some the
design funds needed to complete design and develop both the permit and bid packages.
Diversity in Contracting
The project team has worked with the Diversity in Contracting and set a women- and minority-
owned business enterprise (WMBE) aspirational goal of 15% for this project.
DETAILS
As a result of the necessary and lengthy design coordination, the Port has reassessed the overall
project budget and determined a budget increase is warranted, in addition to requesting Port
Commission’s authorization of remaining budget.
The value of this request incorporates all known cost increases to close out design, prepare bid
documents, allow the Designer of Record to provide minimal design support during construction,
and allow for project management by a Consultant Project Manager.
Project estimates are consolidated in the table below with the additional $1.55 million increase
reflected within the current estimate.