Taxiway A Circuit Replacement (CIP# C801303)
Design and Construction Authorization
Seattle-Tacoma
International Airport
Item No. 10b_supp
Date of Meeting March 26, 2024
Taxiway A Circuit Replacement Request
2
Request Commission authorization for the Executive Director to
authorize final design and preparation of construction bid documents;
advertise, award, and execute a major public works construction contract;
procure long lead items;
include a Project Labor Agreement for the contract; and
authorize use of Port crews for abatement work.
The amount of this authorization request: $39,205,000
Project Background and Scope
Project Background
Taxiway A was constructed in 1987, and centerline lighting has never been
reconstructed.
According to FAA Advisory Circular, any circuit with megger reading below 1
megohm is deemed as “destined for rapid failure”. Taxiway A centerline
lighting circuits exhibit signs of distress with megger readings close to 1
megaohm.
Furthermore, the conduit housing the circuit is corroded, making a cable pull
unfeasible.
Scope
This project will install new Taxiway A centerline lighting circuits, LED light
fixtures, constant current regulators, PVC conduit, and concrete panels
above conduit.
3
Project Details
This project will be combined with the 2025 Airfield Pavement and Supporting
Infrastructure Replacement Project (CIP# C800930) and 2025 Airfield Utility
Improvement Project (CIP# C801177). These projects have overlapping work
areas and design functionality, interdependent operational impacts, and share
2025 schedule milestones. As such they were planned, designed, and phased
to be delivered concurrently for purposes of Airfield safety, efficiency, and
minimization of operational impacts.
4
Project Diagram
5
2025 Airfield Pavement and Joint
Seal Replacement
Taxiway A Circuit Replacement
Project Schedule
6
Schedule
Design complete 2024 Quarter 4
Construction start 2025 Quarter 1
In-use date 2026 Quarter 1
Project Budget
7
Cost Breakdown
Amount of this Request Total Estimated Project
Cost
Design $6,282,000 $6,577,000
Construction $30,527,000 $30,527,000
Sales Tax $2,396,000 $2,396,000
Total $39,205,000 $39,500,000
Operated by the
Port of Seattle
FlySEA. org
Thank
You!
8