
COMMISSION AGENDA – Action Item No. 8h Page 2 of 5
Meeting Date: February 13, 2024, Commission Meeting
Template revised June 27, 2019 (Diversity in Contracting).
Diversity in Contracting
The office of Diversity in Contracting has been involved in Acquisition Planning and strategy
discussions. The total of this work has been planned to take place over several years with
milestone goals to contract some portions using small and, or WMBE firms to perform the work.
There is a goal of spending 10% of the construction costs using WMBE and Small business
resources.
DETAILS
This project was originally budgeted for $850,000 for 2021 to replace waterline which at the time
was failing or in poor condition, totaling 3,000 LF of pipe replacement only. Seed funding was
authorized by Kenneth R. Lyles followed by Commission Authorization of $250,000 total, for
design. Through the design process it was realized that significant improvements in seismic
bracing and other code requirements were needed when replacing the domestic waterline. The
design assessments of all the piping and needed improvements suggested that 100% of the
domestic waterline should be upgraded. The current estimate for construction is $4,500,000
which does not include the portion to be replaced by U00554/U00704 Berths 6 & 8
Modernization project.
The scope of work has been evaluated in terms of piping sections requiring immediate
replacement, areas requiring replacement in 1-3 years, areas requiring replacement in 3-6 years
and those areas which have been replaced due to failure but require seismic upgrades and valve
replacements. Approximately 80% of the existing piping has yet to be replaced and 100% requires
seismic upgrades and other improvements.
Port of Seattle Engineering has completed a comprehensive design for replacing all the existing
galvanized domestic waterline and bringing the system up to current seismic and sanitary code.
The design is currently under floodplain code review at SDCI and all permitting, other than
Mechanical, is expected to be complete by February of 2024.
Portions of this work may be contracted to serve the most efficient delivery while coordinating
with other project work, Operations, and avoiding rework.
Scope of Work
Port Crafts will replace existing galvanized steel piping with new stainless-steel piping, fittings,
valves and supports. Seismic bracing will be installed to comply with current seismic code
requirements.
Schedule:
(1) 2024, Replacement of 400’ of piping, Seismic Upgrades to 800’ of piping.
(2) 2025, Replacement of 1,000' of piping, Seismic Upgrades to 1,000' of piping
(3) 2026, Replacement of 1,000' of piping, Seismic Upgrades to 1,500' of piping
(4) 2027, Replacement of 1,000' of piping, Seismic Upgrades to 1,500' of piping