
COMMISSION AGENDA – Action Item No. 10e Page 3 of 9
Meeting Date: February 13, 2024
Template revised June 27, 2019 (Diversity in Contracting).
direct connection for vessel sanitary sewer, and replacing existing creosote piling with
cement and recycled steel materials.
Diversity in Contracting
The project team has coordinated with the Diversity in Contracting Department to determine
appropriate Women and Minority Business Enterprise aspirational goals for this project and
identified a 5% contracting goal for the major works contract advertisement.
DETAILS
Berths 6 & 8 are the last remaining original timber pier berths at Terminal 91 and are at the end
of their service life. Approximately 30% of the apron is condemned, and the remaining sections
are posted with severe load limits. Originally built in the 1910s, this section of Pier 90 was most
recently rehabilitated in 1985, and little has been done to the structure since then.
Redevelopment of Berths 6 & 8 is critical to ensuring the long-term viability of the port as the
home to the North Pacific fishing fleet.
Planned redevelopment includes demolition of approximately 62,250 square feet of condemned
existing timber apron and replacement of approximately 780 linear feet of seawall (northerly
portion of Berth 6 and entire Berth 8), removal and relocation of existing gangway, floats and
boathouse, removal/replacement of existing small office structures, and reconstruction of a
concrete apron structure at 600 pounds per square foot along the current alignment. The project
includes the removal of over 2,200 failing creosote piles, installation of approximately 320
concrete and steel piles, with an overall decrease in overwater coverage. The project work also
includes stormwater improvements, upgraded shore power connections, renewable energy
through new solar panel arrays, and a direct connection for vessel sanitary sewer.
In January of 2020 the Port Commission authorized staff to proceed with the design and
permitting phase of the project, and in August of 2023 authorized construction funding and the
advertisement of the major works contract. Staff has since completed the design and submitted
application packages for all required environmental permits and engaged important stakeholders
such as the Suquamish and Muckleshoot Tribes, City of Seattle’s Department of Construction and
Inspection, the Army Corps of Engineers, U.S. and Washington State Fish and Wildlife, NOAA
Fisheries, Washington State Department of Ecology, the Port's Neighbors Advisory Committee,
Port operations staff and current tenants in the design development. Demand for moorage at
Terminal 91 is strong. Several times during the shoulder seasons the load-limited and condemned
berth space at Terminal 91 impeded the facility’s ability to accommodate the needs of the North
Pacific fleet and other commercial vessels, research vessels and ships of state. This project will
also allow the Port to remain ready to respond to future business opportunities. This project
responds to the sustained demand and will alleviate some of the shoulder season pressure by
providing space for three 250-foot-plus catcher processors.
As noted in the 2017 Fishing Vessel Moorage Analysis for the Port by S2 Strategy, “fishing and
seafood processing sector of the maritime industry, has by far the largest revenue impact to the
state of any maritime sector. And is at least equal in job production to the other sectors.…”