A GC/CM pre-construction portion of the Contract was executed on August 9, 2019, between the Port
and M.A. Mortenson (Mortenson). The initial Not-to-Exceed amount was $1,500,000 and pre-
construction had an estimated performance period of three years. On August 18, 2020, an EC/CM
contract was executed between Mortenson and VECA Electric & Technologies (VECA), and in
November 2020, Mortenson and VECA mobilized and began providing preconstruction services. At the
time of the initial agreement, design was 30% complete and it was expected that additional funds would
be needed to support the pre-construction services being provided by the GC/CM and EC/CM, although
the full level of effort and services needed was difficult to fully quantify. Therefore, the Port and
Mortenson agreed to begin with the initial NTE funding of $1,500,000 and increase the NTE amount
once the full level of effort and costs for the services could be more accurately defined. In August of
2021, an additional $1,500,000 was authorized through a Change Order to fund the remainder of the
Pre-Construction services. The total budget for pre-construction was $3,000,000.
The Project replaces Main Terminal's low-voltage distribution system at Seattle-Tacoma International
Airport (SEA), which serves power to every floor of the main terminal and is at the end of its serviceable
lifespan. The Project replaces nearly 300 separate electrical power panels and installs a new power
center. Pre-construction services include detailed design reviews with recommendations to improve
quality and reduce project costs. During construction, work performed by the GC/CM and EC/CM will be
negotiated directly as part of the maximum allowable construction costs (MACC). All remaining work is
competitively bid by the GC/CM with Port oversight. The total budget for the project is $119,557,000.
Construction is estimated to be completed in the second quarter of 2026.
SEA's medium voltage electrical distribution system and power centers have all been renewed and
replaced within the last 20 years. The next phase of SEA's renewal and replacement program for the
electrical system is the low-voltage system. This infrastructure is critical to airport operations. Large
portions of the existing low-voltage electrical distribution system are over 40 years old and are past the
end of their useful operating life (30 years), raising concerns over their continued reliability. Additionally,
much of the existing equipment is not compliant with the current National Electrical Code (NEC). This
Main Terminal Low Voltage System Upgrade will correct all the issues in this area and bring the
installation up to current standards and compliance with current codes. Specific scope items include:
(1) Normal Power renewal, replacement, optimization, and expansion.
(2) Emergency Power renewal, replacement, optimization, and expansion.
(3) Replacement of the Central Terminal Power Distribution Load Center.
(4) Implement branch circuit level energy metering in new work.
(5) Minimize disruption to normal airport operations during construction.
(6) Abatement of regulated materials as incident to the overall scope.
The construction contract was executed with Mortenson and the Port in November 2022 and will be
completed in early 2026. The total cost of the Project is budgeted at about $120 million, with a 7%
Women-Owned and Minority-Owned Business Enterprise aspirational goal.