Wi-Fi Improvements Project Passenger Loading Bridges
July 11, 2023
Commission Day
Item No. 8e_supp
Meeting Date: July 11, 2023
Why Ramp Wi-Fi?
Ramp Wi-Fi provides robust ramp coverage for airline and Port operations (baggage
handling, inspections, etc). A common system was established to eliminate each
airline having to deploy their own system
This solution reduces the overall costs of managing multiple systems, having to
move them when gate assignments change, and eliminates the interference
associated with competing systems
The system will also provide ramp level coverage for the traveling public for hard
stand operations
2
Executive Summary
Phases 1 6 complete. Installed Wi-Fi in the Concourses, South Concourse, Main
Terminal including bagwell and Ramp areas close to the building.
Phase 7 installs Wi-Fi on Passenger Loading Bridges (PLBs) on all concourses except
the North Concourse.
Construction of first Phase 7 locations is nearing completion. Budget and estimate
issues require resolution for the remainder of the phase.
Costs for construction of Phase 7 for Main Terminal and South Concourse PLB
Wi-Fi have increased. Request additional budget to cover increased cost.
Phase 8 installs Wi-Fi on PLBs on the North Concourse.
Design of Phase 8 is complete. Request construction authorization to complete
North Concourse installation.
3
Wi-Fi Project: Phasing Scope and Authorizations
Phase 1
Phase 2
Phase 5
Phase 3
Phase 4
Completed 2017
Completed 2018
Phase 8
Phase 6
Phase 7
Todays Request
Construction
Underway
Completed 2017
Completed 2017
Completed 2018
Completed 2017
Concourse C Ramp and Interior
Concourse A, B, D, South Satellite Exterior
South Concourse Interior
Concourse D Interior
Central Terminal; Ticketing
Bag Claim; Bagwell; Gina Marie Lindsey Hall
Passenger Loading Bridges at Concourses A, B, C, D and S Satellite
Passenger Loading Bridges at North Satellite
Construction Package 1
Authorized May 2016
Construction Package 2
Authorized Aug 2017
Construction Package 3
Authorized Feb 2021
Construction Package 4
Requesting Authority Today
4
Overview of Project Cost Increases
May 2016
Budget Incr. $796,000
Total Budget $10,676,000
Cost Drivers
Scope addition: added
more antennas to fill in
coverage gaps found
during surveys
February 2021
Budget Incr. $5,765,000
Total Budget $16,441,000
Cost Drivers
PLB design/construction
complexities
Scope addition: added
North Concourse PLB
Wi-Fi to the project
(formerly part of
NorthSTAR program)
Todays Request
Budget Incr. $2,685,000
Total Budget $19,126,000
Cost Drivers
Material & equipment
price increases and
cost escalation ($1.6M)
Staff time and other soft
cost increases due to
schedule delays ($1.1M)
5
August 2014
Budget Incr.
Total Budget $9,880,000
Cost Drivers
Initial authorization
Remaining Phase 7 and 8 Scope
6
Phase 7
Phase 8
First PLB Installation Progress
7
New Wi-Fi
antenna
New equipment
boxes
Budget / Authorization Summary
8
Schedule
Complete Construction as follows:
Concourse D Q4 2023
Concourse C Q2 2024
Concourse N Q2 2024
Concourse A Q4 2024
Concourse S Q2 2025
9