COMMISSION AGENDA – Action Item No. 8e Page 2 of 5
Meeting Date: July 11, 2023
Template revised June 27, 2019 (Diversity in Contracting).
this project will provide up to 200% increase in the coverage and number of access points on
concourse levels, tenfold increase in bandwidth, and support today’s technology on wireless
protocols for newer devices. Airline operations will benefit from the added Wi-Fi coverage at the
aircraft parking areas and continue to strongly support this project.
Since its initial authorization in 2014, the project has had three budget increases. In 2016, the
budget was increased by $796,000 to cover the cost of additional antennas needed to address
gaps in signal coverage at areas where antennas were previously installed. In 2021, the project
budget was increased by $5,765,000 to account for more complex design and construction and
to add Wi-Fi coverage to the North Concourse PLBs which were not installed as part of the
NorthSTAR program. This commission action is the third budget increase.
Diversity in Contracting
The design contract was awarded back in 2015 that had a Small Contractor and Supplier (SCS)
goal of 7% and is currently achieving 7.4%. For construction, the project team plans to continue
utilizing existing Job Order Contracts which is achieving 9% of a 10% WMBE aspirational goal.
DETAILS
This budget increase of $2,685,000 has two factors: Construction costs went up by $1,588,000,
primarily due to material and equipment price increases both realized and forecast, and the
resulting sales tax increase, and due to the change to JOC delivery. Port staff and designer costs
went up by $1,097,000, due in part to project delays leading to a longer schedule duration
impacting project management costs, more overlapped construction phases impacting
construction management costs, and a need for additional designer construction support.
Multiple projects at the Airport have worked together to provide Wi-Fi coverage across the
Airport terminal buildings. Previously, the ‘Fiber to Backstands’ project provided Wi-Fi to the
interior of Concourses A and B. Phases 1 – 6 of this project have provided high speed Wi-Fi to the
interior of Concourses C and D, South Concourse, Central Terminal, TSA Checkpoints, Gina Marie
Lindsey Hall, Ticketing and Baggage Claim and the Airport ramp areas. The International Arrivals
Facility (IAF) project has provided Wi-Fi within the new IAF facility.
Scope of Work
The project will install Wi-Fi antennas or Wireless Access Points (WAPs) on PLBs to enhance the
Wi-Fi coverage at the Airport. Construction is through the Job Order Contracting (JOC) alternative
public works construction method.
The key elements of project’s scope of work include the following:
(1) Installation of WAPs, surge arrestors, and other necessary mounting equipment.
(2) Relocation of existing installed equipment to meet coverage requirements.
(3) Provision of necessary cabling to connect WAPs to Port network and communication
system.