Exhibit A – Scope of Work and Schedule
2
of contamination. The Port will also submit a copy of the Health and Safety Plan (HASP) for
the project.
The SAP will identify the proposed number and location of all sediment samples, methods,
and depths, and will include a QAPP. The SAP will describe the sampling objectives, the
rationale for the sampling approach (based upon the identified data gaps), and plans for data
use, and shall provide a detailed description of sampling tasks. The SAP shall describe
specifications for sample identifiers; sampling equipment; the type, number, and location of
samples to be collected; the analyses to be performed; descriptions of sampling equipment
and methods to be used; sample documentation; sample containers, collection and handling;
data and records management; and schedule.
The QAPP will be prepared in accordance with the Guidance for Preparation of Quality
Assurance Project Plans, EPA Region 10, Quality Data Management Program, QA/R-5 and
requirements of the EPA Contract Laboratory Program. The QAPP will also follow Ecology’s
Guidelines for Preparing Quality Assurance Project Plans for Environmental Studies (July
2004 – revised July 2016)
1
and the SCUM II.
2
Laboratories must meet the accreditation
standards established in WAC 173-50. In the event that these Guidance documents conflict,
the Port will consult with Ecology.
The SAP, including the QAPP, will be submitted to Ecology for review and approval. As
with all environmental work at the site, work may not begin without written approval from
Ecology. The plan shall provide seven (7) days’ notice to Ecology prior to beginning
sampling. Ecology may obtain split samples.
The Port will provide Ecology with an Agency Review Draft FS Work Plan. Once Ecology
reviews and approves the FS Work Plan, it will be considered the Final FS Work Plan. The
FS Work Plan shall not be implemented until approved by Ecology. Once approved by
Ecology, the Port will implement the Final FS Work Plan according to the Schedule in this
Exhibit.
The Port shall prepare two (2) copies of the Agency Review Draft FS Work Plan and submit
them, including one electronic copy each in Word (.doc) and Adobe (.pdf) formats, to
Ecology for review and comment. After the resolution of Ecology’s comments on the Agency
Review Draft FS Work Plan and after Ecology approval, the Port shall prepare three (3) copies
of the Final FS Work Plan and submit them, including one electronic copy each in Word
(.doc) and Adobe (.pdf) formats, to Ecology.
TASK 5. T91 FIELD INVESTIGATION DATA REPORT
The Port shall conduct field sampling and analysis in general accordance with the SAP and
QAPP. Deviation(s) from the approved SAP and QAPP must be communicated by the Port
to Ecology promptly and documented as required by Ecology.
The Port shall prepare the T91 FS Field Investigation Data Report that describes the results
of all field sampling and analysis. The Port shall provide laboratory analysis data in electronic
format when it has been validated. Raw laboratory data will be provided to Ecology upon
request.
1
Found at https://fortress.wa.gov/ecy/publications/summarypages/0403030.html
2
Found at https://fortress.wa.gov/ecy/publications/documents/1209057.pdf