PORT COMMISSION MEETING MINUTES Page 2 of 5
TUESDAY, APRIL 18, 2023
Minutes of October 27, 2020, submitted for review on November 5, 2020, and proposed for approval on November 10, 2020.
7. PUBLIC COMMENT
Public comment was received from the following individual(s):
• The following people spoke in support of Agenda Item 10a, Language Access Order:
Joaquin Uy and Heather Worthley.
• The following person spoke in support of the cruise and the cruise season: Michael Woody,
Visit Seattle.
• In lieu of spoken comment, written comments regarding Tub Lake and the importance of the
environment to native species were submitted by: Michele Smith.
• In lieu of spoken comment, written comments supporting Agenda Item 10a, Language Access
Order were submitted by: Matias Valenzuela, Public Health, Seattle and King County.
[Clerk’s Note: All written comments are combined and attached here as Exhibit A.]
4. SPECIAL ORDERS OF THE DAY – None.
8. CONSENT AGENDA
[Clerk’s Note: Items on the Consent Agenda are not individually discussed. Commissioners may
remove items for separate discussion and vote when approving the agenda.]
8a. Approval of Minutes of the Regular Meeting of April 11, 2023.
8b. Authorization for the Executive Director to Increase Project Budget by $4,639,000, for
a Revised Total Budget of $14,656,000; to Execute a Professional Services Contract
for Design Services; to Prepare Design and Construction Bid Documents; to
Advertise and Execute a Major Works Construction Contract for the Installation of the
Secondary Air Compressor Portion of this Project; and to Utilize Port Crews for Pre-
Construction Activities and Abatement, for an Amount Requested of $3,500,000, and
an Estimated Total Project Cost Not-to-Exceed $14,656,000, for the Deaerator and
Condensate System Upgrades Design and Construction Project at the Central
Mechanical Plant. (CIP# C801223)
Request document(s) included an agenda memorandum and presentation.
8c. Authorization for the Executive Director to Increase the Project Scope and Associated
Budget by $1,000,000 for a Final Revised Total Budget of $15,000,000 and to Purchase
One Passenger Loading Bridge and Associated Equipment for Gate B11 at Seattle-
Tacoma International Airport. (CIP# C801180/CIP# C801308)
Request document(s) included an agenda memorandum.
The motion for approval of consent agenda items 8a, 8b, and 8c carried by the following vote:
In favor: Calkins, Cho, Hasegawa, and Mohamed (4)
Opposed: (0)