
COMMISSION AGENDA – Action Item No. 8b Page 2 of 5
Meeting Date: April 18, 2023
Template revised June 27, 2019 (Diversity in Contracting).
JUSTIFICATION
These DA and condensate systems including the tanks, associated piping, and pumping are at
their end of life and suspected to be near failure due to age and use. Failure of these systems
would render the Airport unable to use the boiler system as designed until they are replaced.
This would result in a lack of hot water for the airport, meaning restaurants and lounges would
no longer be able to operate.
This project will have a potential net energy use reduction. Installing more energy efficient
pumps, variable frequency drives (VFDs), and upgrading the 50-year-old systems should improve
the CMP’s overall efficiency.
Diversity in Contracting
Part of the design services will be completed using an existing IDIQ contract that was established
in 2022 which has a 17% WMBE participation utilization requirement. WMBE goals will be
evaluated for the remaining project specific design services.
DETAILS
Scope of Work
Key elements of this project include:
(1) Add a second air compressor to mechanical room 211 to serve as a backup when the
three Joy air compressors are removed from the CMP.
(2) New backup air compressor to be supplied with emergency power.
(3) Remove and dispose of the Boiler Room air handling unit to allow access to the DA and
condensate tanks and piping.
(4) Remove and dispose of the three Joy air compressors and the associated air dryers and
receivers, to allow access to the DA and condensate tanks and piping.
(5) Remove and replace the DA (1 tank) and Condensate (1 tank) tanks and piping as
required to support the three 30,000 lbs./hour steam boilers and one 40,000 lbs./hour
steam boiler.
(6) Remove and replace the blowdown and flash tank capable of supporting the three
30,000 lbs./hour steam boilers and one 40,000 lbs./hour steam boiler.
(7) Remove and replace the feedwater pumps and piping and condensate pumps (6 pumps
total).
(8) Install three new VFD's and install feedwater controls as required to the three feedwater
pumps.
(9) Install VFD's for the three condensate pumps to improve efficiency.
(10) Relocate (permanently or temporarily) two Siemens DDC Panels (HCP Nodes 10 and
11) located in the project area. The panels were replaced in 2016 and do not need
replacement but they are a physical obstacle. The panels control / interface with the
boiler operating equipment and will need to be evaluated during design for phasing
impacts depending on whether new systems are installed in parallel.