
Template revised January 10, 2019.
COMMISSION
DATE: December 5, 2023
TO: Stephen P. Metruck, Executive Director
FROM: Arthur Kim, Capital Project Manager III, Waterfront Project Management
Stephanie Jones Stebbins, Managing Director, Maritime
SUBJECT: T5 Dredging Additional Funding
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to increase the total costs not to
exceed from $1,100,000 to $3,500,000 for executing a change order for upland disposal of a
portion of the T5 Dredging Project under Port of Seattle management, Master Identification No.
U00680.
EXECUTIVE SUMMARY
Project budget authorization increase is requested to issue a change order to Orion Construction
to dispose of approximately 5,700 cubic yards (CY) of sediment at an authorized uplands disposal
facility as it is not suitable for in-water disposal.
JUSTIFICATION
This project went from a single phase of construction to two due to unforeseen circumstances.
The original project scope (Phase I) was to dispose of all dredged material identified during
sediment characterization as unsuitable for open water disposal. During dredging of material that
had been characterized as suitable for open water disposal, a sheen was discovered that resulted
in approximately 3,200 CY of material disposed of at an approved upland disposal facility.
Upon completion of Phase I dredging, it was discovered that areas of the berth were under-
dredged. All the approximate 2,500 CY of under-dredged material has been deemed unsuitable
for in-water disposal by the regulatory agencies. Due to this, the dredged sediment will need to
be disposed of at an approved upland facility. The under-dredge work will be completed by
December 31, 2023, and are considered a part of Phase II of the T5 Dredging Project.