
Template revised April 12, 2018.
COMMISSION
DATE: November 3, 2023
TO: Stephen P. Metruck, Executive Director
FROM: Nick Milos, Manager, Corporate Facilities
Rod Jackson, Capital Project Manager
SUBJECT: P69 Underdock Utilities Replacement: Roll-Up Door, Change Orders, Time
Extension, and Additional Funding Request (C801102)
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to: (1) Execute change orders to
contract MC-0320697 which will reduce the contractor’s scope of work and avoid equipment
delays, additional contract suspension charges, and other impacts due to unforeseen regulatory
compliance requirements. (2) Approve a change of scope to design, acquire permits, and
construct a new fire-rated roll-up door to meet regulatory requirements related to the
installation of electrical equipment required for future expansion of vessel shore-power. (3)
Approve the use of Port Construction Services (PCS) and/or Marine Maintenance labor to install
the new electrical equipment, the fire rated roll-up door and related structural components, fire
rated gypsum wall board, and infill a concrete floor depression. (4) Increase project authorization
in the amount of $2,226,000 for a total authorization of $6,701,000.
SUMMARY
The current contract scope of work includes installation of a larger electrical panel that will
provide future expansion of shore power electrical service. During an inspection, the SDCI
electrical inspector determined the new electrical panel would not meet code requirements due
to proximity to the existing metal roll-up door which is not fire rated. The action requested will
allow us to meet code compliance.
The additional funds requested will be used to cover the cost of change orders, design,
construction, utilization of PCS and/or Marine Maintenance labor, soft costs associated with the
extended contract duration, and will provide additional funds for project contingency. This work