COMMISSION AGENDA – Action Item No. 8d Page 2 of 5
Meeting Date: December 12, 2023
Template revised June 27, 2019 (Diversity in Contracting).
recommending that remaining sensors and cameras be delivered via a major public works
contract.
Schedule delays to the design of the fourth phase of the project and the recommended change
in contracting method have resulted in increased project costs estimated at $2,494,000. Finally,
an amendment to the contract with the project system vendor, SAAB, Inc. will provide additional
contract capacity to provide additional sensors and equipment necessary to complete the
system.
JUSTIFICATION
The SAM system provides a holistic view or understanding of underlying reasons or root causes
for delays, bottlenecks, or deficiencies and improve overall airfield efficiency at the Airport.
Additional funding through this request will allow the system to be constructed as designed
providing the greatest opportunity to provide this holistic view.
Diversity in Contracting
The project team has worked with the Diversity in Contracting Department to establish a 10%
women- and minority-owned business enterprise (WMBE) aspirational goal for this construction
contract.
DETAILS
Since 2022 the project has encountered delays due to extensive site investigations during design
and efforts to value engineer alternative locations, additional compliance measures identified
later in the process and the resulting added design effort. These delays have resulted in additional
staff costs and other soft costs. As design neared completion, it was determined that the JOC
construction method approach initially planned for the entire project was no longer suitable for
that entire scope. The JOC construction method utilizes established fixed period indefinite
quantity indefinite delivery public works contracts to complete work in work orders of limited
size. They often prove most useful for smaller scopes of work or repetitive construction of similar
scopes of work.
While a useful tool under the right circumstances, JOC contracting has limitations that would
have extended the delivery time for this project even further, and subsequently increased costs
due to the longer delivery process. As the project team considered alternative delivery methods
to complete construction, a need for more immediate installation of key sensors to address a
critical shortfall of airfield awareness led the team to proceed with the construction of these
critical sensors using the JOC method, while separating out the balance of the work to be
delivered via a more traditional major works construction bid package. While this reduced the
time taken to provide these critical sensors, it resulted in two construction packages and
additional costs to manage both.
Lessons learned because of the challenges this project has faced include: