SEA Parking Garage Rehabilitation (#C801307)
Design Services Procurement
Preliminary Project Work
Item No.
8h_supp
Date of Meeting November 21, 2023
Preliminary Project Work includes:
• Facility Assessment Report (FAR)
• Preliminary design
• Cost estimates
Evaluated facilities and systems
included in FAR:
• Architectural
• Fire suppression
• Mechanical/HVAC
• Power (medium voltage)
• Storm drainage
• Structural/ seismic
Parking Garage Rehabilitation
2
Request Commission Authorization for Executive Director to execute a
project-specific design services contract and complete the preliminary
project work.
Project Location
3
Architecture
Existing Facility Condition
Fire Suppression Structure/Seismic
4
Project Budget and Schedule
5
Project Budget: $55,709,000
This Request : $ 2,100,000
Airline MII approval not required
Preliminary Project Schedule:
• Preliminary Design Complete Q4 2024
• Design Complete Q1 2026
• Begin Construction Q2 2026
• Complete Construction Q4 2027
Cone of Certainty
6
We are here