
COMMISSION AGENDA – Action Item No. __8h__ Page 2 of 5
Meeting Date: November 21, 2023
Template revised June 27, 2019 (Diversity in Contracting).
and taxi) operations. In 2022 public parking generated $88.9 million, and ground transportation
generated $20.8 million, in operating revenue for the Port.
Diversity in Contracting
The project team working with the Diversity in Contracting Department has set an aspirational
goal of 20% for women and minority business enterprises (WMBE) participation in the design
services contract.
DETAILS
The SEA Parking Garage was constructed in three phases; the oldest central portion dating back
to 1969 and has reached its 50-year asset life, and two outboard expansion phases that were
constructed in the 1990s. Aging facilities have an increased frequency of failing infrastructure
and systems, or systems become outdated and no long support the operational need or meet
current code requirements, and the SEA Parking Garage is no exception. Separate efforts have
already been completed, or are underway, that have addressed communications, lighting, low
voltage power, revenue control, and vertical circulation systems within the facility. This project
will address the remaining facility components including architectural, fire suppression,
mechanical/HVAC, medium voltage power, storm drainage, and structural/seismic.
The completion of the project will require the procurement and execution of a project-specific
design services contract with a total contract value of $5 million. This Commission
authorization request only includes preliminary project work, so only a portion of this contract
value will be utilized. Future Commission authorization will be required to utilize the remaining
value of this contract.
Scope of Work
As part of the preliminary project work, a facility assessment report will be completed that will
identify facility deficiencies, code requirements, and estimated costs to address these
deficiencies or requirements. These efforts will be prioritized and programmed as part of this
project, or future projects, to extend the service life of the facility. Preliminary design will also
be completed to validate the budget and schedule requirements for the defined project scope.
Port staff anticipates that the project scope will include the following:
• Architectural: The installation of new or replacement of failed or failing weatherproofing
membranes and required accessibility improvements.
• Fire Suppression: The replacement or upgrade of the two separate fire suppression systems
in the facility to meet code requirements.
• Mechanical/HVAC: The replacement or upgrade of existing ventilation systems to meet
code requirements.
• Medium Voltage Power: The replacement or upgrade of the medium voltage power system.
• Storm Drainage: The replacement of failed or failing infrastructure, and a new connection
into the storm drainage system instead of the industrial wastewater system providing
capacity relief for SEA’s industrial wastewater treatment plant.