
Template revised January 10, 2019.
COMMISSION
DATE: November 3, 2023
TO: Stephen P. Metruck, Executive Director
FROM: Keri Stephens, Director AV Facilities & Capital Programs
Eileen Francisco, Director Aviation Project Management
SUBJECT: Flow Meter Replacement CMP Design and Construction
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to (1) prepare design and
construction bid documents for Flow Meter Replacement in the Central Mechanical Plant (CMP),
(2) advertise, bid, and execute a major works construction contract, execute related project
change orders, amendments, work authorizations, purchases, contracts, and take other actions
necessary to support and deliver the Flow Meter Replacement project within the approved
budget, (3) use Port of Seattle crews and small works contracts to support the design and
construction activities. The amount of this request is $4,165,000 for an estimated total project
cost not to exceed $4,235,000.
EXECUTIVE SUMMARY
This is a renewal and replacement project that will be replacing flow meters and some isolation
valves in the CMP which are at their end of life. The flow meters are critical to the operation of
the entire cooling system. It provides cooling to the terminal building and concourses, as well as
all other critical mechanical, electrical and data communication rooms. Additionally, select
isolation valves were identified as needing replacement in conjunction with the flow meters
because they are not properly sealing and stopping the water flow as intended. New isolation
valves on the condenser supply and return side of equipment will ensure adequate equipment
isolation during project construction, regular maintenance, and emergency operations.
JUSTIFICATION
The cooling system consists of chillers, heat exchangers, water loops, and cooling towers. The
flow meters are essential for the efficient operation of these systems. In 2019, four flow meters
in two of the cooling towers failed and had to be replaced by a separate project. This project will
be replacing the remaining cooling systems’ flow meters to mitigate unplanned outages and loss