Template revised April 12, 2018.
COMMISSION
DATE: October 17, 2023
TO: Stephen P. Metruck, Executive Director
FROM: Cassie Fritz, Manager, Waterfront Project Management Program Controls
SUBJECT: Infrastructure Indefinite Delivery, Indefinite Quantity Professional Service
Agreements
Total Requested Project Cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to execute up to three (3) Indefinite
Delivery, Indefinite Quantity (IDIQ) professional services agreements for Infrastructure related
consulting and design services with a cumulative total amount not to exceed $9,000,000 and a
contract ordering period of five years. No funding is associated with this request.
SUMMARY
Waterfront Project Management Program Controls proposes to advertise and select qualified
firms to provide consulting services. If authorized, the procured services will replace existing IDIQ
contracts that have reached their capacity limits.
The service agreements resulting from this request will allow Port staff to respond to a range of
infrastructure project needs, including, but not limited to:
•
Stormwater drainage systems.
•
Electrical power and lighting systems, low voltage, and telecom systems.
•
Pressurized utilities such as domestic water and fire mains and natural gas lines.
•
Roadways and elevated roadway structures, pavement sections, and traffic analysis.
•
Permitting assistance and compliance.
•
Landscape and public shoreline access.
• Adherence to the Seattle Municipal Code (SMC).
This procurement will allow the Port to responsibly manage finances by providing a cost-
effective means of managing projects that have variable workloads, are time-sensitive, and
require specialized expertise.